|
The House Committee on Energy and Commerce
Full Committee on Energy and Commerce
September 4, 2003
09:30 AM
2123 Rayburn House Office Building
Introduction and Background
Good Morning, Mr. Chairman and Members of the Committee. My name is Gordon van
Welie, and I am the President and Chief Executive Officer of ISO New England
Inc., the independent system operator of the bulk power grid that serves the six
New England states. I am accompanied today by Stephen G. Whitley, ISO New
England's Senior Vice President and Chief Operating Officer.
By way of background, I joined ISO New England in 2000 after serving as Vice
President and General Manager of the Power Systems Control Division of Siemens
Power Transmission & Distribution LLC, where I worked closely with electric
utilities on control systems involving generation and power supply reliability.
An electrical engineer with a graduate business degree, I have twenty years of
experience in the electric power industry in both the United States and South
Africa.
Steve Whitley has been in charge of ISO New England's operations since 2000. He
was previously with the Tennessee Valley Authority ("TVA") for thirty
years, starting as an electrical engineer and progressing through a variety of
positions which gave him responsibility for control area operations, power
supply, economic dispatch, system protection, transmission security and
services, and dispatching for TVA's six-state service territory. He was also in
charge of the planning, design, and construction of the TVA transmission system.
He is currently Chairman of the Electric Power Research Institute Grid
Operations, Planning and Markets Working Group. Steve is available for comment
today regarding operational matters, including the effect of the blackouts in
our region and ISO New England's response thereto.
ISO New England's Role as Independent System Operator
ISO New England, an independent, non-profit corporation, is responsible for the
reliable daily operation of New England's bulk electric generation and
transmission system, which supplies approximately 14 million people. The system
has an installed capacity of more than 31,000 megawatts. There are more than 350
generators and plants and over 8,000 miles of high voltage transmission lines in
our region, and we have 12 interconnections with neighboring systems in New York
and Canada. ISO New England's mission also includes fair and efficient operation
of the region's $4.5 billion wholesale electricity marketplace, and it has been
tasked by the Federal Energy Regulatory Commission ("FERC") since 2000
to assess and plan for the regional system's short-term and long term
reliability needs.
Roles and Responsibilities in the Electric Power System
Before addressing the Committee's specific questions, comment on today's
restructured electric industry might be helpful. Different entities handle
different functions in today's restructured electric industry. In New England,
which constitutes one of the most mature and advanced electricity markets in the
country, there are generators, transmission and distribution companies,
marketers and the independent system operator. Generation is increasingly
provided by unregulated entities who compete to sell their power into the
marketplace, hoping to achieve satisfactory returns on their unregulated
investments in generating plants. Transmission and distribution companies
distribute electricity to customers on a regulated basis, using their own
transmission and distribution lines, including protective devices which are
designed to protect equipment in the event of power system disturbances and keep
disturbances from spreading. These utilities earn an allowed return from rates
which are a blend of transmission rates set by FERC and distribution rates
established by state regulators. Marketers buy and sell generation to
transmission and distribution companies.
An independent system operator, sometimes operating through satellite control
centers with differing degrees of authority and autonomy, administers the bulk
transmission grid and dispatches power from generators onto the grid in
accordance with system demands and reliability criteria. With several different
players having replaced yesterday's vertically integrated utility, the need for
clear delineations of responsibility and authority today is an increasingly
pressing matter.
The New England Power System
Much of the bulk power system in New England was constructed on sound
engineering principles in the late 1960's, and while it was constructed to
accommodate future growth, the demand for power and the demands placed on it by
competitive markets have outstripped the system's design.
The market structure we administer in New England has been successful in
attracting approximately 10,000 megawatts of new generation to the region since
1999, representing almost a third of the system load in peak season, and we
believe the new standard market design we have just recently implemented
provides more accurate market signals to incent the location of generation
nearer to load centers. The market signals provided by the standard market
design also more accurately value the availability of generation supply, such
that in times of scarcity, wholesale market prices rise, which in turn creates
an incentive for the building of new generation capacity. New generating plants
sited in New England over the past five years have significantly increased
regional generating capacity, but these plants have typically been built in less
populous areas far removed from areas that are in the most need of generation.
While this suggests the need for added transmission capability to get surplus
power to customers, the increased investment in generation has not been matched
by investments to upgrade the transmission grid. Our major problem in New
England, and we are typical of many areas in the country, is therefore in
delivering the power from generators to customers. Surplus generating capacity
is not helpful if transmission cannot take it where it is most needed, nor can
the economic benefits of a competitive market for electricity be fully realized
if surplus generation cannot be accessed due to transmission constraints.
Our ongoing planning efforts, which result in an annual planning document known
as the Regional Transmission Expansion Plan, have identified three particular
areas where major transmission improvements are needed: Southwest Connecticut,
Northwest Vermont and Greater Boston. Nearly a billion dollars in new
transmission projects are underway or planned to meet the needs of these
transmission-constrained areas.
Experience tells us that efforts to improve the transmission grid will run into
problems. First, existing incentives for investment in new transmission may be
inadequate in terms of return, certainty of recovery, and uncertainty of
approval. Transmission investment must be made more attractive and process
barriers must be reduced. Second, the regulatory approval process has become too
long, too expensive and too uncertain. Potential transmission applicants need
greater assurance that the approval process will be fair and efficient. Third,
reliability has become politicized, and state regulatory bodies who must approve
or deny applications for new transmission facilities and other equipment
installations come under tremendous pressure in dealing with such applications.
Politics should not be allowed to detrimentally affect reliable service.
The Transmission Siting Approval Process
As the Committee has invited comment which might help to prevent future
disruptions, and as we believe siting and regulatory approval processes are
relevant to efforts to install new transmission infrastructure needed for system
reliability, we would like to offer observations and suggestions based on recent
and pending regulatory proceedings in our region.
A. The Siting Approval Process Needs More Efficiency
In July, Connecticut regulators approved a 22-mile transmission line crossing
five towns, the first leg of a 345kV loop which will relieve system inadequacies
in Southwest Connecticut, the most affected area in our region during the
blackouts. Despite general acknowledgement of the need to improve electric
service in Southwest Connecticut, the transmission application was not well
received by towns and residents along the proposed route when Northeast
Utilities began pre-application consultation activities with municipalities in
July, 2001. The result, after formal filing of the application in
October, 2001, was grass roots pressure on the siting process, executive and
legislative involvement in transmission siting issues, a one year legislative
moratorium on the proceeding, a task force to review the siting of transmission
facilities, and the passage of legislation which will add considerable time,
expense and uncertainty to the transmission siting approval process in
Connecticut. The line was ultimately approved in July, 2003 -- almost three
years after it was filed. And this was after a hearing schedule which spanned
several months, consideration of more than twenty proposals, and eventual
consent by the applicant to use a less preferred underground cable technology
for a considerable portion of the route.
An approval proceeding involving the second leg of the 345kV loop, a 52 mile
line, lies ahead. The full 345kV loop serving Southwest Connecticut will not be
completed until 2008 at the earliest. In the meantime, customers will continue
to be exposed to the possibility of service disruption and higher prices.
There is clearly a need for a speedier, more efficient process for siting
approval, especially as siting decisions in one state can affect the operation
of the electric grid in several other states - as should be apparent from the
events of August 14th. Since bulk transmission facilities operate in interstate
commerce, it is appropriate to provide that if state regulators are unable to
conclude siting proceedings within a certain amount of time, federal authorities
should take over the process. States should certainly retain primacy in
approving transmission siting, but we favor federal backstop authority when
states cannot act in a timely manner.
B. Mandatory Reliability Standards Will Benefit Regulators by Depoliticizing
Reliability
ISO New England contributed to the siting approval proceeding for the first leg
of the 345kV loop in Connecticut by providing reliability studies comparing the
ability of different proposals to meet the need for improved electric service in
Southwest Connecticut. We used national reliability standards adopted by the
North American Electric Reliability Council ("NERC") and regional
standards adopted by the Northeast Power Coordinating Council ("NPCC").
Opponents of the proposed transmission line included state officials and
affected towns who claimed that our reliability studies were flawed because our
test cases assumed, in their estimation, that too many generator or transmission
line outages could occur at the same time, thus subjecting the various
alternatives under study to too many contingencies and overstressing them to
unrealistic extremes. Even when opposing experts conceded that it was
appropriate to overstress the system for planning purposes, they asserted that
transmission lines should not be designed to deal with the more severe multiple
contingency scenarios envisioned by planners.
In effect, Connecticut siting regulators were being urged by governmental
officials to approve a lower voltage transmission line than necessary to meet
reliability standards. I mention this not as criticism of any particular party's
right to present its views, but as an indication of the need to adopt mandatory
reliability standards in order to fortify state siting officials against
localized pressures to do less than what is necessary to assure reliability. I
applaud the Connecticut Siting Council for reaching an appropriate decision in
the face of considerable opposition, but mandatory reliability standards would
have made their decision easier and should facilitate decision-making in other
areas of the country.
Responses to Committee Questions
Q. What exactly were the specific factors and series of events leading up and
contributing to the blackouts of August 14?
As the blackouts began in other regions, it is difficult for me to speculate on
the specific factors which contributed to them. I assume others are better able
than I am to answer this question. As the Committee undoubtedly knows, the
Department of Energy and the North American Electric Reliability Council ("NERC")
are engaged in an intensive fact-gathering exercise to determine what happened,
and I will be interested in their conclusions.
Q. At what time did your company first become aware that the system was
experiencing unscheduled, unplanned or uncontrollable power flows or other
abnormal conditions and what steps did you take to address the problem? Were
there any indications of system instability prior to that time?
ISO New England control room operators first became aware that the system was
experiencing a disturbance at 4:10 pm (EDT). There had been no prior indications
of problems on the New England system prior to that time.
Q. Which systems operated as designed and which systems failed?
In the recent disturbance which affected much of the Northeast, we were able
to isolate most of the New England grid from the rest of the power system. The
New England system was designed and maintained properly and worked as expected.
Automatic protective relay devices on the transmission lines opened as intended,
interrupted the transmission lines and opened the ties interconnecting our
system with New York. This mechanical action separated most of New England from
the disturbance to the west. While power was lost in limited areas, the rest of
the system was rebalanced and saved from a system-wide collapse. Of the limited
areas in our system which were affected, I would suggest that Southwest
Connecticut was hardest hit because its transmission system is the weakest part
of our New England system and it could not withstand the disturbance. The 115kV
transmission lines serving Southwest Connecticut cannot carry as much load as
the 345kV lines serving the rest of Connecticut. Thanks to extensive training in
restoration and an annual system restoration procedure exercise, our operators
were well prepared to bring back power. Our operators adhered to their training
and used the tools available to them within clearly established lines of
authority, and we were able to restore power to many customers in the limited
areas in our system which were affected, mainly in Southwest Connecticut, within
approximately 12 hours. I regret that any customer lost power, but I believe ISO
New England did an outstanding job under the circumstances of August 14. The
coordination within the Northeast Power Coordinating Council ("NPCC")
was excellent throughout the disturbance and system restoration.
Q. If events similar to those which happened on August 14, 2003 had happened
a year ago, would the results have been the same? If similar events occur a year
from now, do you anticipate having in place equipment and processes sufficient
to prevent a recurrence of the August 14 blackout?
Answering from the perspective of New England, being at the eastern edge of the
disturbance, I would have expected similar results in our region if a similar
set of events had occurred elsewhere a year ago. The protective relays in our
system were audited by NPCC approximately a year ago and were in good condition,
so I assume they would have worked. However, Southwest Connecticut's dependence
on a 115kV transmission system would probably have made it similarly vulnerable.
We have been deeply concerned over the last few years that Southwest Connecticut
could experience significant outages because it is a major load center served by
a very constrained transmission system. We simply cannot provide reliable
service to a 3,500 megawatt load center with a 115kV transmission system.
Until 2008, five full years from now, when installation of the full 345kV
transmission line will hopefully be completed in Southwest Connecticut, we will
continue to be concerned that this area could experience significant outages. As
load continues to grow, it is my belief that events similar to those which
occurred on August 14 could have similar effects in our region: most of the
system would separate from adjacent systems, but Southwest Connecticut would
remain challenged by its weak transmission system. Southwest Connecticut's
growing demand for electricity has outpaced ISO New England's ability to assure
reliable service to the people who live and work there. We have also identified
Northwest Vermont and Greater Boston as areas of concern.
I strongly support the regular maintenance program within New England and
administered by NPCC to assure that all protective equipment is properly
installed and in proper working order, and I advocate the continued thorough
review and standardization of operating procedures and training so that both
operators and equipment will be prepared to respond in the event of a recurrence
a year from now. As noted, 345kV lines in certain areas of concern will not yet
be in place next year but will eventually help in the event of a recurrence.
Please see my comments below in response to the Committee's question regarding
prevention of similar incidents in the future.
Q. What lessons were learned as a result of the blackouts?
ISO New England and the rest of the electric power industry in the Northeast are
attempting to reconstruct exactly what happened, and the Department of Energy
and NERC are working together to determine the causes of the blackout. We are
still very much engaged in a learning exercise, and it may be appropriate to
revisit this question after all the facts are established. In the meantime, we
should probably all look closely at the way we operate our systems, the
territory they cover, the decision-making structure and lines of authority, and
applicable operating procedures and reliability standards.
The operators at ISO New England know what the security limits are on the
transmission system - thermal, voltage and stability. This knowledge is derived
from both "on-line" and "off-line" software tools which are
run periodically, in order to determine the security limits of the power system
under a variety of operating conditions. The operators are trained to
proactively operate within those limits in real time operation. They take
immediate action when loading exceeds those limits, even if this means
curtailing demand in a local area. I believe this operating posture was key to
New England's ability to minimize the August 14 disruption and stay balanced
following separation from the rest of the eastern power grid.
Q. How can similar incidents in the future be prevented?
The short answer is to increase the reliability of the electric system and to
operate the system in a secure and analyzed state. We have several thoughts
about how this objective should be accomplished. Upgrading infrastructure is an
obvious priority, but the answer goes beyond that. We know that there are limits
to public acceptance of transmission facilities and other infrastructure
necessary for a reliable and uninterrupted supply of electricity. It is not
realistic to expect reliability enhancements without infrastructure upgrades or
improvement without investment, but aside from infrastructure issues we have a
duty to maximize our ability to operate whatever system we have as reliably and
cost effectively as we can. To this end, I would like to offer four policy
recommendations which I believe will greatly improve the reliability of the bulk
power grid.
Policy Recommendations
1. There must be a single entity with clear operational responsibilities and
authorities for the bulk power system in a region. ISO New England operating as
a single control area fulfills this need for New England. Our area in New
England is a manageable size, enabling us to operate with only four satellite
control centers, without the need to yield operating autonomy to them. They
provide information to the operators in our main control center, and the
operating decisions are made by ISO New England. Creating a Regional
Transmission Organization in New England will further define our operational
responsibilities and authorities.
In other areas of the country, size and operational responsibilities and
authorities become very important considerations in creating and defining
Regional Transmission Organizations. While it is difficult to describe what the
"right" size of a regional area of control should be, size is
nonetheless a very important consideration in creating Regional Transmission
Organizations. A regional area of control must be large enough to track regional
flows and have sufficient operational flexibility to be able to deal with a
reasonably wide range of contingencies. However, as we have recently
experienced, in an extreme emergency, operational control will rest on the
shoulders of one or more human operators and, therefore, the area to be
controlled cannot be too large. The accuracy of software tools supplied to
operators are dependent on complex mathematical models, which in turn rely on
accurate data being transmitted from the field. In emergency situations, these
data sources can be compromised, thus further increasing the dependency on human
interaction. In summary, there is a trade-off between size (in terms of regional
"vantage point") and complexity, and
achieving a reasonable balance between the two is paramount.
In addition to size, clear operational responsibilities and authorities must be
well defined. There must be documented a clear split of responsibilities between
the Regional Transmission Organization and the transmission entities (including
satellite control centers or control areas). Lack of clearly defined operational
responsibilities between the Regional Transmission Organization and the
participating transmission entities can be a major potential source of
operational risk, particularly under emergency conditions. Cascading outages
occur, as you have seen, in a matter of moments. There is no time for questions
of overlapping responsibility, confusion of roles, or hesitant action. If you
have only seconds to prevent voltage collapse and cascading, decisions regarding
the redispatch of generation, reconfiguration and balancing of the system, and
curtailment of transactions and firm load cannot be scattered among the system
operator, satellite control centers, utilities and independent transmission
companies. The control of the transmission system must be consolidated in one
Reliability Authority which would not delegate its duties to underlying
authorities and thus could be held clearly accountable for system operation. For
this reason, we believe that reliability would be enhanced through proper
implementation of the Regional Transmission Organization concept. The RTO, as an
independent transmission provider, would have clear operational control and
authority over the transmission grid in its region. The separation between
planning for system reliability and implementing system reliability measures
would be significantly narrowed, if not eliminated.
2. Reliability standards must become mandatory and operating procedures must
be standardized. Adequate reliability standards do exist today, but to ensure
regional reliability they must have teeth. Reliability standards must become
enforceable, with penalties, to assure that appropriate, modern equipment will
be in place, that it will be properly maintained by trained personnel, and that
there will be enough personnel to operate and maintain the system in accordance
with reliability standards.
Clear standards for transmission operation are also necessary, with standardized
grid management rules and operational procedures, including adequate security
limits, so that operators in every region will be better positioned to
coordinate actions with their counterparts elsewhere in response to critical
events. Right now we have procedural seams between our regions, and standardized
operating rules would help eliminate them. I would be glad to volunteer the
procedures utilized by ISO New England as a detailed and well-proven model. A
core principle embodied in these procedures is to operate the power system in a
secure and analyzed state. To supplement the concept of seamless operating
procedures, I would also suggest an overview system whereby the status of the
entire grid, including actual voltages, power flows and scheduled transactions
could be monitored at the NERC and provided to each RTO Reliability Coordinator
in real time.
Referring again to the incredible speed with which voltage collapse can cascade
into widespread outages, the first line of defense protecting one system from a
disturbance in an adjoining system is mechanical. Mandatory reliability
standards will encourage Reliability Coordinators and control areas to assure
the readiness of their security analysis and alarm systems at all times.
Mandatory standards will promote proper maintenance to assure that such
important equipment as protective relay devices will always respond to
transmission trouble and interrupt faulted lines before they cascade into other
systems.
If automated protective mechanisms fail to contain a system collapse, the second
line of defense against cascading outages is human, and the likelihood of
appropriate human response will be greatly increased by standardized operating
procedures. Control room operators must take immediate action to get and keep
the system within safe operating limits. This will prevent cascading blackouts.
They must be empowered to immediately adjust any or all generating and
transmission resources. They must also be empowered to immediately take load off
the system. Operators must have a reflexive mastery of these procedures and must
follow them in times of crisis with confidence in the knowledge that their
counterparts in adjacent systems are following the same procedures.
3. We must have new infrastructure, which means that we must provide new
incentives for transmission owners to build new infrastructure. Right now the
task of gaining approval for new transmission infrastructure is discouragingly
costly, uncertain and time-consuming, with no assurance of regulatory approval
and cost recovery, and clearly, the financial incentives for undertaking the
task may not currently match the risks involved. Ways must be found to reduce
process disincentives and assure appropriate investment incentives, including
tax credits, to make transmission investments more attractive and to assure
recovery of investment and an adequate return. Finally, it must be clearly
understood that there will be significant costs for improving the reliability of
the electric system, and that the costs will have to be paid by someone, most
probably the customer who will ultimately benefit from both increased
reliability and access to competitively priced electricity in an expanded
marketplace. It is important to note that transmission infrastructure cannot,
and should not, occur on an ad-hoc basis. It should occur pursuant to a
deliberate evaluation of the overall adequacy of the bulk power system in a
region, taking into account inter-regional dependencies. This can only be
achieved with a systematic planning process, such as that currently employed by
ISO New England and a number of other system operators. Such a planning process
should also be mandatory, since it becomes the basis for exposing power system
weaknesses on both a regional and national basis.
4. A balance must be struck between the interests of states to site
transmission facilities and the importance of such facilities in the reliable
operation of the regional electric system. A state should have the first
opportunity to act upon any application for siting approval. However, in
instances of serious transmission constraint or congestion, appropriate federal
authorities should be empowered to issue permits for new transmission facilities
if the public interest requires such a facility to relieve constraints and a
state has failed within a reasonable time to act upon a permit application or
has unreasonably conditioned approval of the project.
Thank you for your consideration.
Printer
Friendly |