|
The House Committee on Energy and Commerce
Full Committee on Energy and Commerce
September 4, 2003
09:30 AM
2123 Rayburn House Office Building
Mr. Chairman, Members of the Committee. My name is Nicholas P. Winser. I am a
fellow of the Institution of Electrical Engineers and have twenty years
experience as an electrical engineer. I am Group Director for transmission of
National Grid Transco plc, which is an international energy delivery business
focusing on the transmission and distribution of electricity and natural gas in
the United States and the United Kingdom. I am also Chief Executive Officer of
National Grid Company, the subsidiary of National Grid Transco that owns and
operates the high voltage electricity network in England and Wales.
I am testifying today on behalf of National Grid USA, whose public utility
subsidiaries transmit and distribute electricity in New England and New York
State. National Grid USA's subsidiaries are no longer active in the electric
generation business, having divested substantially all of their generating
assets. In addition, National Grid USA's independent transmission company
subsidiary, GridAmerica LLC, has executed contracts under which it will
undertake certain responsibilities for the management and planning of the
transmission assets of three major electric utilities in the Midwest, once all
required regulatory approvals are obtained.
Thank you for inviting me here today to address the events of August 14th and
their implications for national energy policy. National Grid is pleased and
honored to assist you and your Committee in the investigation of these events
and in developing a comprehensive set of policies to strengthen the transmission
grid.
This inquiry is of particular importance to National Grid, since approximately
900,000 customers served by its New York subsidiary, Niagara Mohawk Power
Corporation, lost power during the August 14th blackout. Fortunately, Niagara
Mohawk personnel, working closely with the New York Independent System Operator,
Inc. (NYISO), were able to restore power to all of those customers within about
seven hours. While the immediate impact of the August 14th blackout on National
Grid's customers was thus temporary, it was disruptive. The blackout serves as a
reminder that electricity consumers are heavily dependent on the integrated
interstate electricity delivery system that is straining under the weight of
current demands.
National Grid is committed to strengthening and expanding the transmission grid
in the United States, not only by adding new transmission facilities, but also
by making maximum use of existing facilities and rights-of-way. National Grid
hopes that the unfortunate events of August 14th will underscore for
policymakers the urgency of developing and implementing policies that will
promote the establishment of a reliable and robust transmission infrastructure
throughout the United States.
In this statement, I will respond to the specific questions that you have asked.
As you requested, I will address the important policy questions that must be
considered if we are to enhance the reliability of the electric transmission
grid and thereby minimize the risks of a repetition of the August 14th blackout.
The Events of August 14th
We do not yet have a complete picture of the underlying causes and contributing
events that led to the August 14th blackout, though it appears that the initial
events took place off National Grid's system. National Grid has been cooperating
fully with the joint U.S.-Canadian investigation of these events, as well as
other investigations, and will continue to do so. Based on preliminary review of
available data, we can provide the following description of the
"cascading" effects of the initial disruption on National Grid's
system.
So that the Committee may understand how events occurring on other utilities'
systems, in this instance apparently in the Midwest, could have such profound
effects on service to customers on adjoining systems, it is necessary first to
explain briefly some of the principles upon which the interconnected alternating
current (AC) electric transmission system operates. In order to control power
flows on an AC electricity system, the frequency at all locations on the grid
must be synchronized. (The interstate AC grid in the United States operates at a
design frequency of sixty cycles per second.) This in turn requires that load
and generation on the grid remain in close balance at all times. If there is a
mismatch between load and generation on a particular portion of the grid, the
frequency at that location will attempt to deviate from the desired level.
Because the frequency is synchronized across the grid, energy will move across
the grid in an attempt to compensate for the local imbalance. This can lead to
uncontrolled power flows and severe damage to transmission and generation
equipment. System operators keep some generating capacity synchronized as
operating reserves in order to enable them respond to relatively small
short-term fluctuations in supply and demand, including unanticipated outages of
generation.
To prevent damage to equipment when large imbalances between load and generation
occur, automatic protective systems are in place (many of them installed after
the 1965 blackout) to respond to situations in which the frequency deviates
outside of a very narrow band around the acceptable system frequency. Generating
equipment has protective systems that disconnect it from the transmission system
if frequency deviates outside the tolerable range (whether high or low) in order
to prevent damage that could otherwise render the generation unavailable to
restore the system and serve load after the incident.
An additional and extremely important measure put in place after the 1965
blackout as a means of restoring the balance between load and supply following a
major disturbance, was the introduction of the automatic capability to reduce
demand (referred to as automatic under frequency load shedding). While the use
of automatic load shedding, as a last resort, plainly inconveniences the
affected customers, it prevents the disturbance from spreading and causing
equipment damage, which would affect more customers by delaying even further the
restoration of service. The need to rely upon automatic protection systems such
as programmed load shedding can be reduced by good operating practices, through
which the delivery capability of the system is monitored and analyzed on an
ongoing basis and actions taken in response to changes in the configuration of
the system before extreme and uncontrollable conditions result.
With that brief introduction in mind, I will turn to the August 14th blackout.
On August 14th, the systems of National Grid and other utilities in New York
State were affected by external events occurring within a very short period of
time. From information made available by the North American Electric Reliability
Council (NERC), it appears that a significant mismatch between load and
generation developed in the Midwest (though we received no notice of the
emerging conditions at the time). This caused large and abrupt swings in power
flows and frequency, and protective systems tripped several transmission lines
in New York State at approximately 4:10 p.m. This was the first indication we
received of a disturbance.
The electric system in western and central New York State separated from the
system in eastern New York State. The system in western and central New York
remained energized, and some load continued to be served throughout the event.
In accordance with the under frequency load shedding program implemented by New
York utilities in coordination with the reliability councils, automatic
protective systems operated and initiated the controlled shedding of customer
loads in an effort to bring the load and generation into balance. In eastern and
central New York State, service was interrupted to a large number of customers,
though some pockets of load were served in areas where generation was available,
such as the Albany area. In most of eastern New York State, the balance between
load and generation could not be maintained and the system collapsed into a
blackout. As noted earlier, these events took place within a very short period
of time. Indeed, many of the events occurred within a matter of seconds, well
before operators could intervene manually.
The transmission lines connecting the New York electric system and the New
England electric system were also opened by operation of their protective
systems. This separated the systems of New England and the eastern Canadian
provinces from those to the west. Those systems appear to have been affected
less severely by the power swings and voltage fluctuations, enabling them to
remain stable, without further loss of service. In the end, New England only
lost about 2,500 MW of load in Southwest Connecticut, Western Massachusetts, and
Vermont for brief periods.
The Operation of Protective Systems
Preliminary analysis indicates that the protection schemes in place in the New
York/New England region generally worked as intended to prevent more extensive
and long-lasting disruptions. They allowed the system to shut down with minimal
damage to key transmission and generation facilities. Most of the transmission
system in New York State indeed remained intact. While keeping the key
components of the transmission and generation system undamaged did not keep the
lights on for all New Yorkers, doing so was crucial to facilitating the
restoration of service after the event. Had critical transmission lines or
generating stations suffered significant physical damage, the necessary repairs
could have extended the restoration process for days or even weeks in some
areas, depending upon the location and severity of the damage.
On National Grid's delivery system in New York State, approximately 900,000 of
the 1.5 million customers connected to National Grid's delivery facilities in
upstate New York lost service on the afternoon of August 14th. Service was
restored as rapidly as the available generation permitted, with all those
customers back in service within approximately seven hours. The following day,
as part of the restoration process, a small number of customers were again
without power for a brief period, while load was being balanced with the
generation that was coming back into service.
The transmission control centers in New York also appeared to function well
during the event. Back up power supplies to these control centers appear to have
worked correctly. As a result, the control system stayed operable during the
event, and the operators were able to follow established plans and communicate
effectively. This also speeded the restoration process. It allowed the
individual transmission owners to give instructions to the generators in their
individual control areas while the NYISO coordinated bulk power restoration.
The equipment and processes in place in New York State and New England therefore
appear, based on preliminary analysis, to have functioned as they were designed
to perform: to isolate the portion of the grid experiencing the disturbance and
to protect generation and transmission facilities from serious damage when
large, uncontrolled power swings occurred due to events on adjoining systems
(which are still being investigated). The automatic systems that protected that
equipment did so by disconnecting generation and load from the grid and by
opening some transmission lines. Unfortunately, millions of customers lost power
as a result. Each of the systems comprising the interconnected AC transmission
system is affected by conditions on all other systems and we do not yet know
exactly what happened outside of New York to cause the large, unexpected power
swings that appeared on the New York State system. Accordingly, there are simply
too many variables involved to tell whether the results would have been the same
if the events of August 14, 2003 had transpired a year earlier.
Lessons Learned and Policy Recommendations To Enhance Reliability To Guard
Against the Recurrence of Similar Events
Because the investigation into the events that led to the August 14th blackout
is still underway, it is too early to identify the specific technical and
operational solutions that are needed to minimize the likelihood that similar
events might occur in the future. It is important nevertheless to recognize that
continued employment of sound operating principles will reduce the risks that
severe disturbances might occur on the grid in the first place. This will
minimize the need to rely on automatic systems that protect equipment from
damage by disconnecting components and customers from the network when such
disturbances occur. Once the circumstances that gave rise to the August 14th
blackout are identified, I would expect that utilities and system operators will
identify any shortcomings in existing equipment and operating procedures to
prevent those circumstances from repeating themselves.
From a policy perspective, a significant amount of work has already been done
and can still be done to address problems like those experienced on August 14th.
While the investigation into the specific technical and operational issues that
led to the August 14th blackout is not complete, it is critical for policymakers
to take the steps necessary to promote a more reliable delivery infrastructure.
Those steps cannot be limited to generation, transmission, or demand-side
measures in isolation. All of these areas may well form part of an integrated
solution to this complex problem.
For some years, National Grid and others have raised the concern with Congress,
the Federal Energy Regulatory Commission (FERC), and the Department of Energy
that investment in the interconnected transmission system has not kept pace with
generation and load growth and that significant upgrades are needed to maintain
and enhance reliability and expand competitive markets. We have also underscored
the need for active and independent management of the transmission system. As a
result, we strongly advocate energy legislation and regulatory policies that
address the roadblocks to grid expansion and independent transmission operation.
To achieve these objectives, policymakers should focus on the following areas:
- Promoting Independent Transmission Companies. For too long, the electricity
delivery system has been the forgotten element of the Nation's electricity
infrastructure, largely left to fend for itself while market participants focus
on new generating plants. The events of August 14th reveal the dangers of
treating the delivery system as an afterthought. Independent transmission
companies that will focus their business plans on the ownership and efficient
operation of the grid and in making the investments needed to bring it in line
with the demands of the 21st century are critically needed. As proactive
managers and operators of transmission assets they will be well-positioned to
minimize instances when it is necessary to resort to automatic protective
systems. They also will be positioned and motivated to maximize the use of
existing transmission facilities and rights of way. They will be able to make
the needed investments in the energy delivery infrastructure free of competing
demands for generation investments. Moreover, they will promote open and
non-discriminatory transmission service because they have no generation
interests to favor. For this sector to develop, Congress must reform the tax
laws to remove impediments to transfers of transmission assets to new
independent owners and must repeal the Public Utility Holding Company Act, which
limits the expansion potential of independent transmission companies. FERC also
must allow these companies sufficient authority over their assets to enable them
to do the job and enable them to employ performance-based rates that reward
increased efficiency.
- Effective Transmission Planning and Expansion Policies. To ensure that the
transmission grid upon which we all rely is adequate to serve current and
projected needs, regional transmission planning processes must be established to
regularly assess the need for upgrades both to improve and enhance reliability
and to remove bottlenecks that limit customers' access to cheaper electricity.
To be effective, those processes must be streamlined. They must not afford
opportunities for market participants that profit from existing bottlenecks
(because they keep competing suppliers from reaching their markets) to delay or
frustrate needed expansion projects. In particular, needed upgrades must not be
put on hold by requirements that utilities search for voluntary participant
funding or regulators resolve debates over cost allocation. Instead, regional
planning processes should look to the region's utilities to make the grid
upgrades required both to preserve reliability and expand customers' access to
lower cost power.
- Rational and Stable Transmission Pricing. The transmission grid needs
significant upgrades to enable it to handle the increased demands now placed
upon it both for reliability and for efficiency. FERC must establish
transmission pricing policies that give utilities adequate assurance that they
will recover investments in system upgrades. Those policies must recognize, as
the events of August 14th make clear, that customers and generators throughout
the region rely on and benefit from a reliable and robust transmission system
and should bear a fair share of its costs. Policies must also be stable enough
that a utility can rely on them to return its investment over many years and be
simple enough to apply so that critically needed delivery system upgrades are
not delayed by battles to allocate costs to different customer groups.
- Removing Barriers to Siting Transmission Facilities. FERC lacks the authority
to grant certificates for interstate electric transmission projects, even though
it has had that authority for natural gas pipelines for decades. This regulatory
gap makes it profoundly difficult to site, construct, or modernize transmission
facilities, particularly between states and market regions, even when the need
for greater grid capacity is clear. Congress should, at a minimum, grant FERC
backstop siting authority for electric transmission projects.
As policy objectives, these are all key steps toward a regulatory and market
regime that fosters the development of a reliable delivery infrastructure.
FERC's proposed Wholesale Market Platform would make significant progress in
implementing the first three of these policies. It consists of a significantly
revised version of the so-called standard market design that FERC proposed last
year and incorporates many of the comments that FERC received on that proposal
from a broad cross-section of the industry, as well as consumers and state
regulators. Progress on the policies embodied in the Wholesale Market Platform
proposal is essential to the development of independent transmission companies,
effective regional transmission planning, and rational transmission pricing
policies that would facilitate critically needed grid expansion. From what we
have seen, there appears to be no substance to the speculation that electric
industry restructuring and FERC's efforts to develop competitive energy markets
may have contributed to the blackout. To the contrary, National Grid believes
that it is those efforts that will ultimately address reliability concerns, if
they are premised on independent operation of the transmission grid and focused
on the development of a delivery infrastructure that is both reliable and
sufficient to support competitive markets.
Policymakers should also give serious consideration to the content of the
reliability standards that govern the design and operation of the interconnected
electric transmission system. In general, the current reliability standards call
for the transmission system to be designed so that it can withstand the single
largest contingency considered by planners. Many other countries (as well as
portions of the U.S. grid) are designed to more stringent standards. Adopting
more stringent standards generally for the U.S. transmission system would
improve its capability to deal with unexpected power swings without interrupting
service. National Grid believes that closely scrutinizing the content of the
rules themselves and promoting transmission companies focused on planning and
operating to satisfy those requirements is crucial regardless of whether
compliance with the reliability standards is enforced with a new regime of
mandatory rules and penalties.
While the cost of improving the Nation's transmission infrastructure will have
to be borne by customers in their rates, transmission represents only a small
portion of the total electricity bill (ten percent or less in most cases). Since
an improved transmission grid will not only enhance reliability but will improve
the efficiency of energy markets and ultimately lower energy costs to consumers,
even modest energy costs savings are very likely to outweigh transmission
reinforcement costs. Moreover, a more reliable infrastructure will reduce the
likelihood of widespread outages and the resulting costs to the economy.
In short, while the specific technical and operational solutions to solve the
problems of August 14th are still being identified and assessed, it is incumbent
upon policymakers to continue their work to establish a regulatory environment
that fosters the development of a robust transmission grid-one that will ensure
reliability of the entire system and deliver efficient competitive energy
markets.
National Grid appreciates the opportunity to assist the Committee in its vitally
important review of the causes of and solutions to the problems experienced on
August 14th.
Printer
Friendly |