|
The House Committee on Energy and Commerce
Full Committee on Energy and Commerce
September 4, 2003
09:30 AM
2123 Rayburn House Office Building
Good morning, ladies and gentlemen. My name is William J. Museler, and I am
the President and Chief Executive Officer of the New York Independent System
Operator, or NYISO. I appreciate the opportunity to brief the Committee on what
we know so far about the August 14, 2003 blackout and our restoration
operations. My testimony today will focus on the questions raised by the
Committee in the Notice of Hearing.
Immediately prior to coming to the NYISO, I was the Executive Vice President of
the Transmission/Power Supply Group of the Tennessee Valley Authority, which in
terms of MW served, is the size of New York. Prior to that, I was Vice President
of Electric Operations at Long Island Lighting Company. I serve as the Chairman
of the ISO/RTO Council, and have served on the NERC Board and as Chairman of the
Southeast Electric Reliability Council. I am a graduate of Pratt Institute and
Worcester Polytechnic Institute.
The NYISO was created to operate New York's bulk transmission system and
administer the wholesale electricity markets. We are a New York not-for-profit
organization and started operation in 1999. As you know, we are pervasively
regulated by the Federal Energy Regulatory Commission ("FERC"). As
provided in the Federal Power Act, we are also regulated with respect to certain
financings by the New York State Public Service Commission.
ISOs, and later regional transmission organizations ("RTOs"), were
established to help implement the FERC's policies of partial deregulation as
originally set forth in its Order 888, issued in 1996. In its order, FERC set
forth certain functions of ISOs and, in a later order, of entities with similar
functions such as RTOs. ISOs and RTOs generally act as the primary interface
between generators, transmission owners and other participants in the wholesale
electric marketplace. ISOs and RTOs accomplish this by dispatching the power
system in their control area (i.e., directing the power plants to generate a
specific amount of power at a specific time) to supply electricity to customers
while maintaining safety and reliability. In addition, ISOs generally facilitate
and administer a number of different electricity markets, thereby providing
market participants with the ability to sell and purchase various services on an
unbundled basis.
The primary market function of ISOs or RTOs is to ensure fair and
non-discriminatory access to the transmission system. As such, ISOs are meant to
be independent of any individual market participant or any one class of
participants. Reliability and security of the transmission system represent the
other critical functions for a system operator. For example, the NYISO, in
accordance with NERC, the Northeast Power Coordinating Council ("NPCC")
and the New York State Reliability Council ("NYSRC") rules, implements
and adheres to reliability standards intended to ensure that the integrated New
York State electric system has enough generating capacity, including reserves,
to provide a reliable power supply. Although ISOs play a key role in ensuring
reliability, ISOs have only operational control of the bulk power system. They
do not generate power, or own any generating or transmission equipment. They do
not have any financial interest in any transactions for the generation or sale
of electricity.
I would like to make clear at the outset the areas that we know and those that
we do not. While I am, of course, aware of what has been in the press regarding
the events that initiated the blackout in a significant part of the Eastern
Interconnection, I am not yet able to tell you anything in detail about those
events because they have not yet been determined in detail, and details in this
case are extremely important. Because the initiating events happened in a very
short period of time - really just a matter of seconds - and happened away from
New York, understanding them fully depends largely on interpreting electronic
data that we do not have. The International Commission formed by President Bush
and Prime Minister Jean Chretien of Canada is being given the data and is
undertaking its interpretation. We are, of course, cooperating fully in this
investigation. The U.S. end of that investigation is well underway and is headed
by the Department of Energy. Like you, I'm anxiously awaiting their conclusions.
In addition to outside investigations, the NYISO began its own investigation and
analysis within hours of the event. The NYISO is reviewing its own records to
determine the precise sequence of events that took down major portions of the
New York system within fractions of a second. We have, in our preliminary
analysis, identified two uncontrollable power swings that led to the New York
system disturbance that occurred at about 4:11:00 p.m.
Up until the event, our system was operating normally, well within applicable
criteria and with adequate reserves. There had been a routine scheduling call
with adjoining control areas that occurred only 11 minutes before the event (at
4:00:00 p.m.) without indication of a problem. The first indication of a
possible problem somewhere on the Eastern Interconnection occurred at 4:09:09
p.m. in the form of a counter-clockwise 700 MW power swing that flowed from the
PJM control area through New York into the Ontario control area (which is
operated by the Independent Electricity Marker Operator or "IMO"). The
700 MW power swing did not, however, create a system contingency on the New York
system (i.e., the system was still secure and within intended operating
criteria). This 700 MW power swing was not a very unusual occurrence and thus
did not alarm the operators. Such a swing usually indicates that a power plant
or transmission element has failed in another region.
A second counter-clockwise 1100 MW power swing occurred a minute later, at
4:10:40 p.m., again flowing from the PJM control area through New York into the
Ontario control area. At this point, there were approximately 2700 MW flowing
through this New York transmission corridor, consisting of approximately 900 MW
of normal flow compounded by the 700 MW and 1100 MW power swings. Our
preliminary data indicates that seconds thereafter, a 2700 MW reverse power
swing either from or through Ontario into the New York system occurred, which
instantaneously took down major portions of the New York system. However,
several hydro plants in upstate New York, as well as the Quebec tie line,
remained in service, as did the majority of the upstate transmission system.
Thus, about 20% of the New York load continued to receive service during the
disturbance. Unfortunately, New York City was completely without service at this
point.
Immediately after the event, the NYISO began implementing its restoration plan.
The first step in the restoration process involves stabilizing the system and
restoring our ties to the neighboring control areas. After that, the process of
bringing power plants and outside sources back online must take place, including
the delicate balancing of the power they can supply with the demand in the
individual area being restored. If the demand were greater than the supply, the
system would crash in the affected area, and fortunately that did not occur.
Within about three hours, we were able to restore one major tie to the remainder
of the Eastern Interconnection at Ramapo. The first major power plant was
returned to service in just under an hour after that, and a few minutes later we
re-established a transmission path to New York City. Throughout the next day,
there was a painstaking process of bringing generators back to the system and
re-energizing lines. Statewide service was completely restored by 10:30 p.m.
Friday, August 15th. The restoration process followed NYISO's pre-arranged plan
and it worked well.
Preliminary analyses indicate that the New York system operated as designed,
given the event, and that the power swings New York experienced were beyond
anything the system had been designed to withstand.
In an occurrence such as the recent blackout, the greatest danger to electric
service is potential damage to the system itself-the power plants and the
transmission lines. Had that kind of damage occurred, it could have taken days,
weeks, or even months to restore. Fortunately, the complex protective mechanisms
that had been installed on New York's transmission system and on its power
plants worked as intended and no serious damage was done. This protection
shortened the restoration process considerably.
We do not know at this time what equipment, design, or process improvements
would be required to prevent a reoccurrence of the August 14th blackout. It is
important to understand that the facts must drive the measures taken to prevent
a reoccurrence of the August 14th blackout. Until the cause of the cascading
blackouts is ascertained, we cannot anticipate what design changes, preventive
equipment, or process improvements should be put in place. Needless to say, we
will thoroughly review our own operations to determine if they can be improved,
and all of our data and analyses will be forwarded to NERC for use in the
International Commission's investigation.
The events that so affected New York on August 14th are not yet known in
sufficient detail to plan and implement specific solutions. However, we believe
it makes sense to examine the known problems that could give rise to other
reliability concerns in the future. We believe that the reliability standards
set by the NERC, which are now voluntary, should be made mandatory. That issue
is now before the Congress in the energy legislation now before a conference
committee. We also believe those standards should mandate significantly improved
communications and operating protocols among the various regions of the country,
since we are now painfully aware of the extent to which events in one region can
affect neighboring regions. Right now, there is no expectation that a
non-adjacent system operator would communicate to other, non-contiguous control
areas the existence of a condition or disturbance on its system, which is
outside of allowable operating limits. Neither, is there an obligation on the
control area's neighbors to communicate to the control area any information they
obtain regarding problems on other systems. Communications alone, unfortunately,
will not prevent a future blackout from occurring. The goal of having better
communication is to enable ISOs and RTOs to take anticipatory action, if
required, as soon as a system condition or disturbance becomes apparent anywhere
on the Interconnection. Of course, there is no guarantee that prior knowledge or
notice will translate into anticipatory action that can prevent a system
disturbance.
There are some actions that can be taken in New York to help ensure that other
reliability problems do not arise. New York has been short of generation in the
recent past and projections indicate that deficiencies are likely again later
this decade. That shortage will grow and will represent both a reliability
concern and, in our new competitive markets, a cost to consumers. The NYISO has
already reformed its capacity markets to encourage investment in needed
facilities and is working with neighboring regions to develop regional capacity
markets.
New York's transmission grid and its internal planning process needs to be
strengthened. Current incentives for building transmission are inadequate.
Likewise, inter-regional planning processes should be improved, and in the case
of interstate facilities, a federal override (backstop authority) may be
appropriate. I should note that this problem also has a continuous upward effect
on electricity prices, since congestion on our transmission grid inhibits the
free trade in electricity that the competitive markets were designed to foster.
In this brief statement, I have tried to respond to the Committee's questions
and to summarize the state of the investigations into what we know about how we
handled the recent blackout in New York. I have tried to do so without
speculating on things about which it is premature to draw conclusions. Needless
to say, once the results of the international investigation are available, the
NYISO will move aggressively to implement appropriate changes, as indicated by
that investigation. Finally, I have taken the opportunity to alert the Committee
to some of the measures, which can help to avoid future problems.
I want to thank the Committee for the opportunity to come here today, and we
will be cooperating with the Committee and the on-going inquiries into the
outage.
Printer
Friendly |