|
The House Committee on Energy and Commerce
Full Committee on Energy and Commerce
September 4, 2003
09:30 AM
2123 Rayburn House Office Building
A definitive analysis of the contributing events and causes of the August 14,
2003, blackout will take months to complete. At this time, Cambridge Energy
Research Associates' (CERA's) analysis indicates that a combination of normal
component failures, transmission system deterioration, and an inability to
respond and contain the problem at several levels of control caused the
cascading blackout.
At this time, it appears that the greatest power failure in US history began
with normal component failures. For example, one failure on August 14 was an
unplanned outage of a unit at the East Lake power plant that caused power flows
to instantaneously reroute in the transmission network. Such unplanned power
plant outages occur thousands of times each year and so too does the
instantaneous rerouting of power flows. Such normal component failures and
dynamic power flows are part of normal power system operations.
Transmission system operators plan for normal component failures. To do this,
they configure the electrical system-the real-time balancing of sources of power
and uses of power and the limits on transmission line loadings in the system to
withstand the effects of normal component failures. At a minimum, proper
transmission network planning keeps the power system configured in such a way
that it can withstand the effect of the most critical component in the system
failing (first contingency planning). Automatic controls on generating plants
and transmission lines allow the power system to isolate problems, protect
equipment, and reconfigure itself to a stable condition within seconds following
a normal component failure.
As power system conditions change (supply, demand, weather, etc.), power flows
reroute at close to the speed of light. Thus, when a generating unit and a
transmission line trip and power reroutes, several transmission lines carry more
power and, as expected, begin to sag. On August 14, one of these lines carrying
more power near Cleveland sagged close enough to a tree to short circuit. Proper
maintenance (tree trimming) should prevent such contact but, again, transmission
line failures of various types are something power system operators also plan
for. Nevertheless, when power rerouted along the remaining lines, additional
overloading occurred and automatic protections for generating plants and
transmission lines disconnected additional power plants and lines in the
network. At some point, the multiple failures pushed the system past its limits
to isolate and restabilize. Consequently, the problem expanded over a larger
area of the power network as significant rerouting of power flows continued.
When a power system is not configured to contain a normal component failure, the
destabilization of a larger part of the power system quickly follows. Power
surges spread through some parts of the network-Pennsylvania, New Jersey and
Maryland, and AEP-that reacted (both automatically and with discretion) to
isolate themselves in order to maintain stable system operations. However, such
actions add to the rerouting dynamics of the remaining power network and begin
to overwhelm the remaining parts such as eastern Michigan, Ontario, and finally
New York.
The root cause of the cascading blackout appears to be a breakdown in the
planning, coordination, and communication necessary to control the
interconnected power systems. The sequence of events in the blackout caused
parts of the power system to act on their own rather than in a coordinated
fashion. Such coordination has not gotten the proper investments of time, money,
and systems in the past several years and this system deterioration-the
cumulative effects of years of underinvestment in the varied needs of
transmission networks-is a root cause of the blackout.
Past Efforts to Prevent and Minimize Blackouts
The blackouts of 1965 and 1977 in the Northeast and in 1996 in the West spurred
efforts to prevent and minimize blackouts in the future. The lesson from 1965
was that greater integration of regional power systems created desirable
day-to-day benefits from electric trade but required an associated higher level
of planning, coordination, communication, and control to prevent cascading power
outages. As a result, the formation of the North American Electric Reliability
Council (NERC) and its regional reliability councils followed the 1965 blackout.
The lesson from the two blackouts of 1996 in the West was that a breakdown in
planning, coordination, communication, and control can allow normal
events-again, in one case, a power line sagging into a tree-to cascade into a
large regional system failure. In this case, the cascading failure began with
federally owned transmission assets that were highly integrated with other
publicly and privately owned transmission infrastructure. Following the 1996
blackouts, the western power system decreased the amount of power flowing on
transmission lines (forgoing savings from increased power trade) in order to
maintain the level of redundancy necessary to prevent a repeat of cascading
failures following normal component failures. A year or more passed before the
planning and coordination got to the point that these power transfer limits
could return to pre-blackout levels.
The blackouts of 1977 in New York and several years ago in Chicago highlighted
the problem of underinvestment in power delivery systems. In Chicago the problem
was underinvestment in distribution (the small wires near homes) rather than in
transmission (the large wires that carry power long distances). Even the best
planning and coordination to properly manage a power system cannot offset the
problems created by continued underinvestment. Eventually the probability of
multiple component failures and the increasing constraints on systems operators
charged with configuring a reliable power system leads to a major blackout. This
underinvestment affects more than just transmission lines and substations and
includes computer systems, backup systems, software, instrumentation, data,
rules, and organizations.
What Worked on August 14?
The conditions across the eastern power interconnection on August 14 were not
highly stressful. The East was not in the throes of a prolonged heat wave or
suffering from an abnormally high level of supply outages. Interregional power
flows were providing benefits, as areas with higher-cost generation were able to
draw upon areas of lower-cost generation. As the blackout cascaded through the
Midwest, Ontario, and New York the automatic protective devices for power lines
and power plants worked to prevent damage. Restoration of electric service
reflected a well-thought-out and rehearsed sequence of procedures. The control
centers of the electric systems appear to have captured the real-time data
necessary to reconstruct the details of the cascading failure. The blackout
exposed weakness in the US power grid but did not provide evidence that the US
has a third world transmission infrastructure. Normal component failures should
be expected even in a state-of-the-art transmission network. Quite to the
contrary-the high degree of interconnection of the US grid exposed the need for
better planning, coordination, communication, and control.
Needed Improvements
Defining the Transmission Mission
Electric transmission is critical infrastructure in the US economy. The
transmission network is a natural monopoly that is in the middle of an industry
that is stuck halfway between regulation and the marketplace. Transmission
remains in the center of integrated regulated power companies and public power
entities as well as at center stage in emerging power markets, where it governs
the interactions between consumers and producers. A properly structured
transmission sector requires that the institutions and rules meet the needs of
both of these existing industry structures. Transmission policy must adjust to
the reality that regional power systems in the United States will operate for
quite some time with very different structures-some relying greatly on market
mechanisms and others relying on comprehensive regulation. Transmission
institutions and rules must accommodate the different power industry structures
that are interconnected and need to interface properly.
Transmission Organizations
Transmission organizations need to reflect the underlying reality of the
transmission infrastructure. We do not have a seamless, national transmission
grid and are not even close to having one. Instead, the US power system consists
of a dozen regional transmission networks within three largely independent
transmission interconnections, with varying levels of power transfer capability
between regional networks and with networks in Canada. These networks cover
multistate areas and need organizations that align with the physical extent of
the grids to implement the necessary planning, coordination, communication, and
control.
Thus, the Federal Energy Regulatory Commission (FERC) should not allow movement
to the market in regions that do not have proper alignment between the
transmission organization and the network. Currently, the US Midwest network has
two transmission organizations in formation and transition, rather than one, and
suffers a misalignment between the organizations and the underlying extent of
the regional network. On the other hand, if the FERC gains authority to order
regional transmission organization participation in regions moving to the
market, then it should also order proper alignment between transmission
organizations and networks.
Since these regional networks do have significant interconnections, the need
also exists for an umbrella organization to coordinate operations and
interdependencies within the interconnections. We want sufficient overall
control to avoid situations in which one regional network protects itself by
causing collapses in neighboring networks. The current NERC comes close to the
envisioned umbrella organization but suffers from being a voluntary organization
with limited enforcement authority.
Mandatory Reliability Standards and Procedures
Mandatory electric reliability standards and procedures would help address the
breakdown in planning, coordination, and communication that are at the
foundation of power system control. A system of rules and procedures is needed
that provides real-time information flows such that all system operators have a
clear view of not just their local power system but also the larger whole. Such
standards and procedures need to be enforced by an agency with authority over
both publicly and privately owned transmission assets in competitive as well as
regulated industry structures. International agreements are also necessary to
coordinate with Canadian power systems and, to a much smaller extent, Mexican
power systems.
An umbrella organization must ensure that contingency planning evaluates the
power system as a whole-and is not just an uncoordinated set of regional
contingency plans with a blind spot regarding their interdependencies.
Resolving the Gridlock in Transmission Investment
More investment is needed in the US transmission network. Many opportunities
exist where the benefits of additional transmission infrastructure investments
far exceed the costs, and this result is robust under a wide range of future
conditions. The problem, as CERA identified in its 1999 report entitled
Gridlock-Transmission Investment and Electric Restructuring, is that "[c]urrently
there is no entity in the emerging industry structure-neither generators,
transmission owners, independent system operators, distribution companies,
traders, retail marketers, nor end users-facing the proper incentives to
invest." Our conclusion four years ago was that "[s]ustained
underinvestment in transmission may eventually threaten the reliability of the
bulk power system."
Underinvestment in transmission and the gridlock in transmission policy are
longstanding problems. When I last testified before the Senate in July 2002,
CERA warned that a continued lack of investment would lead to reliability
problems: "A gridlock plagues most transmission investment decisions
because incentives are misaligned." These investments "were not being
undertaken because no one faced the full costs and benefits of AC network
investments and was in a position to pursue these opportunities
profitably." Over a year ago, the Department of Energy's National
Transmission Grid Study provided a similar warning. And in CERA's Special Report
Energy Restructuring at a Crossroads: Creating Workable Competitive Power
Markets, 5 out of 12 recommendations on making power markets work involved
transmission issues. CERA's currently ongoing study Grounded in Reality:
Bottlenecks and Investment Needs in the North American Transmission System is
finding that significant transmission congestion exists both within and between
regions.
The solution goes beyond higher allowed regulated rates of return, tax
incentives, or accelerated depreciation. The payoffs already exist. The problem
is settling who pays. The current principle is that whoever benefits ought to
pay. However, implementation of this principle is very difficult. Benefits are
robust under a wide variety of conditions but as conditions change, the
incidence of those benefits can shift dramatically. Transmission investment is
stymied by the complex arguments of who will benefit and thus who should pay. As
a result, adequate investment is not yet being made. Transmission investment
planning at the network level that guarantees cost recovery and prevents
investment indecision due to gridlock on cost allocation and recovery mechanisms
is sorely needed. One possibility is a policy that allows economic transmission
investment identified by analyses at the network level to go forward with a
default decision to spread the costs across the entire network. Reallocations
and true-ups can follow later if necessary and substantiated.
Printer
Friendly |