|
The House Committee on Energy and Commerce
Full Committee on Energy and Commerce
September 4, 2003
09:30 AM
2123 Rayburn House Office Building
Mr. Chairman, members of the Committee, thank you for the opportunity to
appear before this committee and provide AEP's perspective on the August 14th
outage. My name is E. Linn Draper, Jr. I am Chairman, President and Chief
Executive Officer of American Electric Power, the largest electricity generator
and transmission owner in the U.S, with 38,000 MW of generation capacity and
39,000 miles of transmission line. Almost 5 million customers are linked to
AEP's 11-state electricity transmission and distribution grid. The company is
based in Columbus, Ohio. With $5 billion invested in our transmission grid, ours
is a unique perspective.
From the outset, let me be clear, we did it right. The AEP system held together
- a point of pride for us. Our protective systems performed automatically as
they were designed to perform, our operators performed and communicated as they
should and our load and generation remained in balance throughout the day. Our
grid is large, robust and integrated, and can therefore withstand the power
swings we experienced that day. Michehl Gent, NERC President and CEO, on Aug. 15
said AEP's 765-kV transmission system is "often heralded as the world's
finest transmission system."
From an operational standpoint, the 14th was a fairly typical August day until
our operators first detected transmission line problems at an interconnection
point with FirstEnergy, and AEP contacted FirstEnergy's operators. Throughout
this event, we maintained extensive communications with our reliability
coordinator, PJM, and with FirstEnergy.
Power flows before the event, especially into Michigan and northern Ohio, were
high but not unusual, given typical summer loads. It's important to note that
Michigan is often a significant importer of power. Power flows on our lines
continued to increase because of increased demand outside our system. We still
do not know the cause of that increased demand.
As the flows of power exceeded safe operating levels across our lines, our
equipment in northern Ohio operated automatically to isolate the problem. This
is exactly the way the equipment is designed. To quote the DOE's National
Transmission Grid Study, released in May of last year, "electricity flows
according to the laws of physics and not in response to human controls, what
happens in one part of the grid can affect users throughout the grid."
The opening of the lines isolated our system and prevented damage to the
equipment. More importantly, it avoided cascading outages across the AEP System
and probably far beyond, given the central role of AEP's transmission grid in
the Eastern Interconnection. AEP's system was not the only one to respond this
way - the transmission system serving Consumers Power's load, among others, also
isolated from the problem during the event, and their system held. I don't know
why all systems didn't perform in a similar manner.
Automatic tripping of lines is not simply a matter of protecting our equipment.
There are serious reliability and safety implications if the automated
protection mechanisms do not activate.
First, if the equipment is damaged, it can be out of service for an extended
time - further burdening other lines that are, as we all know, already stressed.
In short, the system holds for as long as it can, but at some point equipment
must trip off to prevent further cascading outages. In this instance, tripping
off stopped the cascade to the south, enabling AEP's personnel to assist others
in their restoration efforts, because we were not busy with restorations of our
own.
Tripping off also has safety implications. If current runs as high as it was
during the event, it could actually cause the lines to literally melt or to sag
beyond design criteria, which can result in safety hazards to the public.
I can't speculate on the root causes for this event, so I can't tell you that it
wouldn't have occurred a year ago, or that it will never occur in the future.
The interconnected nature of our grid, and the fact that we're now using it in
ways that it was not originally intended or designed, mean that these kinds of
events can occur in the future, although lessons learned can prevent a
reoccurrence of the same magnitude.
I take great exception to the characterization of the U.S. transmission system
as "third world grid," as some have said. The American transmission
grid is the strongest in the world, although it is being pushed to its limits on
a continuing basis.
The electrical grid in this country was designed in large part to get a local
utility's generation to its customers - not to carry thousands of cross-country
and regional transactions, as the grid is now called to do. In the five-year
period during which wholesale electric competition first gained momentum, the
number of wholesale transactions in the U.S. went from 25,000 to 2 million - an
80-fold increase. And many stakeholders are striving for continued growth.
Needless to say, transmission infrastructure expansion - which is an expensive
and time-consuming prospect at best - did not increase 80-fold in that time
frame. In fact, very little expansion has taken place.
Clearly, there is a need to strengthen the grid through greater investments -
new equipment, new lines and new technologies - to support the grid for the
manner in which it is used today.
Several factors will hasten grid improvement:
First and foremost, we need regulatory certainty. If we need to build new
transmission facilities today, we must navigate through multiple state and
federal regulators to get that done. Processes vary in every state. For permits
and siting, for instance, we must get approvals from multiple state regulators,
and probably multiple federal regulators as well. We proposed a 765-kV line in
West Virginia and Virginia in 1990. After an expenditure of over $50 million, we
received final clearance to build the line this year. While we respect the
interests of all jurisdictions in siting decisions, we'll never get where we
need to be if it takes 13 years to get permission to build a power line.
And for every dollar we spend - and the National Transmission Grid Study quoted
a price of $1.8 million per mile for a new 765-kV line - we must go back to
those multiple state and federal regulators to receive full recovery. In this
context, it is difficult to understand recent actions by the FERC to eliminate
transmission revenues from third party or wholesale customers. If what FERC is
proposing comes to pass, power can move from St. Louis to New Jersey for the
same fee as moving power from Pennsylvania to New Jersey. Such scenarios not
only jeopardize existing investments, they create a disincentive for future
investments since full and fair cost recovery is even more difficult.
Second, and also critically important, we must improve coordination and
communication among the various entities that oversee the grid. The reality is
that we don't have one single transmission grid owner and operator throughout
the country, nor would it be feasible or wise to do so. It's a given that there
will always be seams - or boundaries - between various grid operators.
What's required is continuous improvements in the coordination among the various
grid operators to ensure coordinated planning and operations, and quick response
in emergency situations. On Aug. 14, our operators did coordinate and
communicate with other operators, which helped to prevent this from spreading
even further across the country - but we can all strive to improve. Those who
are using this event to promote their desire for a single RTO administering a
spot market are not only missing the boat, but misleading you and others into
thinking that simply installing such an RTO would answer the reliability issues
that have been raised by this event.
Next, I fear that the current controversy and seemingly endless debate over the
role of RTOs is hindering our ability to make progress and create an environment
that is conducive to investment. While AEP has committed $50 million to RTO
development, many states now are opposing an expansive role of RTOs, including a
number of AEP's 11 states, while others fully support a broad role for RTOs and
more federal control over the grid and the wholesale market.
While debate about RTOs rages on, let's not forget some key points:
· AEP is at the center of the current debate largely because of the quality and
the scope of our system, which is at the crossroads of many markets - that's one
big reason we're coveted by market stakeholders in their attempts to expand.
· Policies should balance both generation and transmission. Transmission owners
must receive sufficient revenues to assure adequate investment.
· Parties that benefit from competitive markets should bear the costs. Those
that use the transmission system to receive those benefits should pay for it.
· While some have even suggested splitting up the AEP system, that's
unacceptable and counter-productive. AEP's system has been touted as the
backbone of the Eastern Interconnect. Splitting it apart amidst efforts to
increase the nation's electric reliability flies in the face of reason.
We need consensus on an appropriate use of the grid. If we focus solely on
competitive markets and economics, serious implications for reliability and
security arise. We need a balance, but that balance must be tipped toward
reliability - the fundamental foundation of the transmission grid. Without
reliability, we have no market to structure.
The benefits of competitive markets should not only flow to generation owners or
electricity users, as seems to be the present policy, but also to the
transmission owners who need to receive a sufficient share of benefits to assure
investment in the transmission infrastructure necessary to support competitive
markets.
Additionally, we must approve NERC as the enforcement entity for mandatory
reliability standards. Our grid is interconnected. We must all play by the same
rules, and we must have a knowledgeable independent entity - such as NERC -
empowered to enforce such standards.
Thank you again for the opportunity to address this committee. We will continue
to work with DOE, NERC and all entities embarking on investigations of the
events of August 14th and look forward to a complete analysis and answer to what
happened that day.
I encourage you to wait until the NERC/DOE investigation is complete to draw
conclusions. Thank you again and I will be happy to respond to any questions
from the Committee.
Printer
Friendly |