Witness Testimony
The Honorable Patrick Wood
Chairman Federal Energy Regulatory Commission 888 First Street, NE
Washington, DC, 20426
Regional Energy Reliability and Security: DOE Authority to Energize the Cross Sound Cable
Subcommittee on Energy and Air Quality
May 19, 2004
10:00 AM
I. Introduction and Summary
Thank you for the opportunity to testify on the operation of the Cross-Sound
Cable (CSC or Cable). The CSC is an underwater direct current 330 megawatt cable
system under Long Island Sound. The CSC connects the New England Power Pool (NEPOOL)
regional transmission system in Connecticut to the New York Independent
Transmission System Operator (NYISO) transmission system on Long Island, New
York. Pursuant to orders by the U.S. Secretary of Energy, the CSC has been used
at times over the past two years to transmit power between these two regions.
However, the Cable is not in operation currently.
I have testified to this Subcommittee before about the critical role that
sufficient energy infrastructure plays in both reliability and in ensuring
customer benefits. (Failure of infrastructure development to keep up with
customer demands certainly played a central role in the California energy market
price spike in 2000-2001). The CSC project is the first operational example of
entrepreneurial, risk-bearing transmission that the Federal Energy Regulatory
Commission (Commission) has sought to encourage in the post-Energy Policy Act of
1992 electric industry. "Merchant" transmission differs from
traditional transmission in that its costs are not recovered through regulated
rates, but through negotiated arrangements between the transmission line owner
and the customer. This is important because the risks of merchant transmission
are borne by the project's investors, and not captive ratepayers. In 2000, our
Commission ruled on the rates, terms and conditions for transmission service
over the Cable, and found that the Cable will enhance competition by expanding
capacity and trading opportunities between the New England and New York markets.
The Commission also found that the Cable will provide economic benefits to
electric customers and producers in both markets while imposing no risk or cost
on captive customers in any market. The Cable may also provide reliability
benefits, particularly at times of electrical shortages. Today, four years after
our Commission authorized rates, terms and conditions for the Cable, and after
investors and wholesale transmission customers have made the necessary
investments to get it built, the Cable is being taken out of operation.
The Cable provides a classic illustration of the interstate nature of the
transmission grid. The planning, construction, and operation of the Cable affect
both the regional marketplace and regional reliability. Decisions regarding the
operation of the Cable underscore the importance of assessing economic and
reliability issues from a regional perspective. Building and operating a
transmission line can have economic and reliability consequences that go beyond
any single State. Therefore, questions about who should pay for those
consequences must, of necessity, be considered in ways that fully protect
customers and citizens of the affected States.
II. Background
On June 1, 2000, the Commission approved the rates, terms and conditions for
transmission service over the Cable (June 1 Order). This was the first time the
Commission approved rates, terms and conditions for a merchant transmission
project. The June 1 Order contained the findings of economic benefits noted
above. The Commission imposed several conditions on its approval. For example,
the application included a proposal to hold an "open season" to
solicit customers for the Cable, and the Commission imposed conditions to ensure
that the open season process was non discriminatory, fair and transparent.
In June 2002, the Commission accepted, with modifications, NEPOOL's amendment to
its open access transmission tariff to integrate the CSC into the NEPOOL
regional transmission system operated and administered by ISO New England
(ISO-NE). The Commission said it was "pleased that the parties worked
together to meet the challenges facing the development of a new type of entity
into the energy market."
Despite the foregoing, and despite the fact that none of the costs of the CSC
are being included in captive Connecticut ratepayers' rates, units of the
Connecticut government have opposed the operation of the Cable. As a result, the
Cable has been operated only when authorized by emergency order of the U.S.
Secretary of Energy - from August 1, 2002 to October 1, 2002 (to alleviate the
emergency supply situation caused by a heat wave), and from August 14, 2003 to
May 7, 2004 (to alleviate the post-Blackout disruptions in electric transmission
service, as well as provide valuable voltage support and stabilization services
for the electric transmission systems in both New England and New York). The
Secretary has issued these orders pursuant to section 202(c) of the Federal
Power Act, 16 U.S.C. § 824a(c) (2000) (FPA), and section 301(b) of the
Department of Energy Organization Act, 42 U.S.C. § 7151(b) (2000).
I would note that Connecticut and Long Island are interconnected not only by the
Cross-Sound Cable but also by a set of electrical cables known as the "1385
Cables." The 1385 Cables have been in use for over 30 years. In recent
years, they have experienced increasing operational problems. A pending case
before the Commission involves a Connecticut utility's request that the
Commission use its authority under section 210 of the FPA to order a New York
utility to assist in replacing the 1385 Cables. Among other things, section 210
allows the Commission to issue an order requiring the physical interconnection
between two utilities, or such action as may be necessary to make effective any
physical interconnection, if, after certain procedures, the Commission
determines that such an order is in the public interest and would: "(A)
encourage overall conservation of energy or capital, (B) optimize the efficiency
of use of facilities and resources, or (C) improve the reliability of any
electric utility system . to which the order applies." Since the case is
pending, I cannot discuss its merits further at this time.
III. Operation of the Cross-Sound Cable
Over the past decade, investment in the nation's transmission infrastructure has
not kept pace with load growth or with customers' desire for greater competition
in wholesale power markets. As a result, transmission congestion and energy
price differentials between regions have increased. Construction of appropriate
transmission facilities and other measures that make more transmission capacity
available to market participants can yield significant benefits in increased
competition and improved reliability. Stand-alone, or merchant, transmission
companies have proposed several projects to expand capacity between regions such
as New England and New York. The Commission has sought to encourage such
projects.
In the case of the CSC, the Commission specifically found that the project would
provide economic benefits to customers. The U.S. Secretary of Energy has found
that, at least in certain circumstances, the operation of the Cable is needed
for reliability purposes. This summer could be one of those circumstances. The
Cable is fully built and ready for use. Operation of the Cable is supported by
one State and opposed by another, each advocating its own parochial interests.
The authority granted to the U.S Secretary of Energy under FPA section 202(c)
has been an important tool for responding to emergency circumstances.
Legislation has been proposed that, essentially, would codify the Secretary's
most recent order requiring operation of the Cable until Congress legislates
otherwise. Operation of the Cable would ensure that the regional benefits of the
Cable will flow to customers.
Further, it might be a good time to consider expanding the application of
section 202(c) to also include orders requiring the operation of existing
facilities whenever such operation is found to be in the public interest, not
just in the event of an emergency. The view of one State should not be the sole
determinant of whether a region's electrical customers receive the economic and
reliability benefits of facilities that have already been built. In these narrow
circumstances, the protection of interstate commerce may warrant a greater
federal role.
This suggestion is related to, but separate from, the issue in the pending
energy bill of having a federal backstop for siting of significant new
interstate power transmission projects. The same conflict that gave rise to that
provision of the pending legislation is present in the Cable case, i.e., while
the interconnected electricity grid is interstate in nature, each State has the
jurisdictional authority to site new transmission lines needed for the region.
Therefore, a federal arbiter is needed when States cannot agree on such issues.
The national public interest in reliable supplies of energy for all customers at
reasonable prices cannot be ignored.
There is also a bigger real-world issue here. The greater New York City electric
power marketplace, which also encompasses Long Island, northern New Jersey and
southwestern Connecticut, is among the largest load centers in the country. The
planning and operation of that regional power grid falls under the management of
three separate grid organizations - the NYISO, ISO-NE, and the PJM
Interconnection. This split requires a continuous, rigorous coordination effort
on many levels - reliability, planning, markets, and fuels. To this end, the
Commission is holding another in its series of regional infrastructure
conferences on June 3, 2004, to explore the adequacy and development of
electric, natural gas, and other energy infrastructure in the Northeast,
including New York and New England. I expect that many of the issues addressed
in this hearing, plus others from the natural gas industry, will be raised in
the day-long conference, which my colleagues and I will lead. I will report on
what we hear to this Subcommittee shortly thereafter.
As always, my colleagues, I and our staff are always available to assist the
Subcommittee in any way we can.
|