Witness Testimony
The Honorable Lee Otis
General Counsel US Department of Energy 1000 Independence Avenue, SW
Washington, DC, 20585
Regional Energy Reliability and Security: DOE Authority to Energize the Cross Sound Cable
Subcommittee on Energy and Air Quality
May 19, 2004
10:00 AM
Mr. Chairman and Members of the Subcommittee, thank you for
inviting me to testify concerning the Secretary of Energy's recent orders
concerning the Cross-Sound Cable and the effect of the Cable's operation on
reliability.
On May 7, 2004, Secretary Abraham issued Order No. 202-03-4, in
which he determined that the emergency giving rise to his earlier orders
authorizing use of the Cable had ceased to exist, and that no other emergency
had been demonstrated justifying continued authorization to use the Cable. The
May 7 order briefly recounts the events leading up to it, but I will summarize
them here, and also will summarize the legal authority that the Secretary used
to issue his Cross-Sound Cable orders.
Section 202(c) of the Federal Power Act gives the Secretary of
Energy the authority to determine that an "emergency" exists, and
"to require by order such temporary connection of facilities and such
generation, delivery, interchange, or transmission of electric energy as in [the
Secretary's] judgment will best meet the emergency and serve the public
interest." It is this authority that Secretary Abraham has used when he has
directed operation of the Cross-Sound Cable.
By its terms, this section of the Federal Power Act is limited
to situations in which the Secretary has determined an "emergency"
exists. However, neither the Act nor DOE's regulations define exactly what an
"emergency" is. The Act does state that an emergency can exist because
of "a sudden increase in the demand for electric energy, or a shortage of
electric energy or of facilities for the generation or transmission of electric
energy, or of fuel or water for generating facilities, or other causes,"
but it leaves to the Secretary's judgment exactly what set of facts and
circumstances might constitute an emergency, as well as the determination of
whether to issue an order under section 202(c) and what terms of such an order
might "best meet the emergency and serve the public interest."
On August 14, 2003, the United States and Canada experienced the
largest electric transmission grid failure and blackout that has ever occurred
in North America. That same day, in order to alleviate the emergency situation
presented by the blackout, the Secretary exercised his authority under Federal
Power Act section 202(c) and issued Order No. 202-03-1, which authorized
operation of the Cross-Sound Cable. The Secretary issued that order after DOE
officials had consulted with the independent system operators in both New
England and New York, as well as officials at the North American Electric
Reliability Council, electric utilities in both Connecticut and New York, and
the owner of the Cross-Sound Cable.
The next day, President Bush and Canadian Prime Minister
Chretien announced the creation of a bi-national task force to investigate the
causes of the blackout and why it
2
spread, as well as to formulate recommendations about what might
be done to prevent blackouts from occurring in the future.
The task force immediately commenced its investigative work, but
because of the immense amount of data and information that needed to be analyzed
and the extensive investigative work that was necessary, it was not possible to
reach an immediate conclusion as to what had caused the blackout or why it
spread. Therefore, on August 28, 2003, and even though electric service had been
restored in the area affected by the August 14 blackout, Secretary Abraham
issued an order finding the continued existence of an emergency, and determining
that operation of the Cross-Sound Cable should continue to be authorized until
such time as he issued an order determining that the emergency had ended.
The next day, August 29, 2003, State officials from Connecticut
filed papers with DOE seeking rehearing of the August 28 order and asking that
DOE stay the operation of the order pending judicial action. Several days later,
the Secretary issued an order calling for the submission of briefs and
information with respect both to the rehearing request and the stay request, and
establishing a schedule for the submission of that information. His order
identified a publicly-accessible DOE website address at which all materials
submitted to DOE would be made available.
In response, numerous persons, including Members of Congress,
submitted letters, data and information to DOE concerning the Cross-Sound Cable
and its operation. All of
3
these submissions were made publicly available, and the public
was given the opportunity to comment on the submissions made by other persons.
At the same time, the work of the bi-national task force
investigating the August 14 blackout was proceeding. The task force issued an
interim report in November 2003 that set forth tentative conclusions concerning
how the blackout began and why it spread to certain parts of the United States
and Canada. The interim report called for public comment concerning all aspects
of the report, and public meetings were held in both the United States and
Canada concerning the interim report. The task force also invited the submission
of written comments and recommendations, which were made publicly available.
In early April 2004, the bi-national task force issued its final
report. That report identified the direct causes and contributing factors for
the August 14 blackout. The report states that the blackout began in Ohio, and
describes in detail the sequence of events leading up to the blackout, and that
occurred as the blackout spread across an area encompassing 50 million people.
The Cross-Sound Cable was not in operation on August 14, 2003,
and the final report did not identify any effect that the non-operation of the
Cable had either on the initiation of the blackout, or on its spread. The final
report simply does not identify any particular role that the Cable would have
played in preventing or stopping the spread of the outage, had it been in
service on August 14, 2003.
4
After issuance of that final report, DOE considered the contents
of the report as well as DOE's earlier analysis of the data and information
that had been submitted in response to the Secretary's call for information
concerning the operation of the Cable. DOE also made its own inquiries of the
relevant Independent System Operators to assess the power supply and
transmission situation in the vicinity of the Cross-Sound Cable.
In light of the reasons for and the terms of the August 28
order, and the data and information submitted to and developed by DOE, the
Secretary determined that the emergency identified in his August 28 order no
longer existed. That order had authorized continued operation of the Cable based
on the finding that an emergency continued to exist because "it has not yet
been authoritatively determined what happened on August 14 to cause the
transmission system to fail resulting in the power outage, or why the system was
not able to stop the spread of the outage." Once those facts were
determined, as they were in the task force's final report, and because that
report did not point to any role the Cable did or could have played in
connection with the cause or the spread of the blackout, the Secretary
determined that the emergency he earlier had identified no longer existed. He
furthermore concluded that the information that the public had submitted to him,
as well as the investigation conducted by DOE itself, did not demonstrate the
existence of any other present emergency warranting continued authorization to
operate the Cable under the authority of Federal Power Act section 202(c).
Therefore, he found that the emergency he had identified earlier ceased to
exist, and he terminated the Federal Power Act section 202(c) authorization to
operate the Cable.
5
As the Secretary stated in his May 7 order, DOE believes the
Cross-Sound Cable is an important transmission asset and contributes to the
reliability of the electric transmission grid in New England and New York. In
fact, the Cable was mentioned in the report of the National Energy Policy
Development Group, in May 2001, as an important transmission asset, the
operation of which had been blocked because the State of Connecticut did not
recognize the importance of the facility to the interstate grid.
It is important to remember that under present law, however,
section 202(c) does not authorize DOE to direct operation of a transmission
facility simply because the facility is important to the grid, promotes commerce
or improves reliability. Instead, the law requires the Secretary to find that
"an emergency exists" before he can invoke his authority to issue a
202(c) order. Therefore, this section of the law was not intended to be a
replacement for the resource adequacy and transmission facility siting
responsibilities carried out by other governmental and private bodies.
Because the Administration believes that existing law is not
sufficient to adequately protect electric reliability and to promote the
construction and operation of needed electric transmission facilities, the
Administration strongly supports the electricity provisions contained in Title
XII of the H.R. 6 Conference Report, which the House approved several months
ago. The bi-national blackout task force stated that the single most important
thing that could be done to prevent future blackouts and reduce the scope of any
that do occur is for Congress to enact the reliability provisions in H.R. 6 and
make
6
compliance with reliability standards mandatory and enforceable.
The Administration also supports repeal of the Public Utility Holding Company
Act and supports last-resort Federal siting authority for high-priority
transmission lines - both of those provisions would encourage investment in
needed transmission and generation facilities.
Finally, I want to emphasize that although there are obvious
limits to the circumstances in which the Secretary can issue an order under
Federal Power Act section 202(c), Secretary Abraham has not hesitated to use
that authority when presented with data and information that, in his judgment,
warrant a finding that an "emergency" exists. He issued an order
directing operation of the Cross-Sound Cable only hours after the August 14,
2003 blackout occurred, and continued the directive to operate the Cable until
it had been determined what happened on August 14 to cause the blackout and why
the system was not able to stop the spread of the outage. He also issued an
order on August 16, 2002, directing operation of the Cross-Sound Cable, because
it had been demonstrated that an emergency existed as a result of imminent
shortages of electric energy on Long Island.
The Department continues to monitor the reliability and
transmission situation in the Northeast and elsewhere in the country. Any person
is invited to bring to DOE's attention, at any time, data or information that
the person believes demonstrates an emergency exists and that the Secretary
should exercise his section 202(c) authority. The Secretary stands ready to
exercise that authority, with respect to the Cross-Sound Cable or any other
situation or facility, if presented with facts that demonstrate an emergency
exists, and that a 202(c) order would alleviate the emergency and would be in
the public interest.
Thank you again for inviting me to testify today. I would be
glad to answer any questions.
|