|
Subcommittee on Energy and Air Quality
April 18, 2002
09:30 AM
2123 Rayburn House Office Building
Mr.
Chairman and Members of the Subcommittee:
We are pleased to be here today to discuss the Department
of Energy's (DOE) project to develop a nuclear waste repository. As required
by law, DOE has been investigating a site at Yucca Mountain, Nevada, to
determine its suitability for disposing of highly radioactive wastes in a mined
geologic repository. On February 14, 2002, the secretary of energy recommended
to the president approval of this site for the development of a nuclear waste
repository. The next day, the president recommended approval of the site to the
Congress. The president's recommendation began a statutory review process for
the approval or disapproval of the site, including action by the state of
Nevada, the Congress, DOE, and the Nuclear Regulatory Commission (NRC) within
specified time frames. If the site is approved, DOE must apply to NRC for
authorization (a license) to construct a repository. If the site is not approved
for a license application, or if NRC denies a license to construct a repository,
the administration and the Congress will have to consider other options for the
long-term management of existing and future nuclear wastes.
Our testimony, which is based on our recent report on the
Yucca Mountain Repository Project,
addresses (1) DOE's readiness to submit a license application within the
statutory time frame, (2) the extent to which DOE can meet its goal of opening a
repository at Yucca Mountain in 2010, and (3) the extent to which DOE is
managing the project consistent with applicable departmental procedures.
DOE is not prepared to submit an acceptable license
application to NRC within the statutory limits that would take effect if the
site is approved. The president's recommendation of the Yucca Mountain site to
the Congress triggered specific statutory time frames for the next steps in the
repository project. Nevada, which had 60 days from
February 15 to disapprove the site, did so on April 8.
The Congress now has 90 days (of continuous session) from that date in
which to enact legislation overriding the state's disapproval. If the
Congress enacts such legislation, the Nuclear Waste Policy Act requires DOE to
then submit a license application to NRC within 90 days of the effective date of
the legislation. Thus, the process gives DOE about 5 to 8 months from the date
of the president's recommendation to submit the license application. However,
in a September 2001 detailed reassessment of the work required to submit a
license application that would be acceptable to NRC, DOE's managing contractor
concluded that DOE would not be in a position to submit the application to NRC
until January 2006, or about 4 years from now. Moreover, while a site
recommendation and a license application are separate processes, essentially the
same data are needed for both. Waiting until DOE was closer to having the
additional information needed to support an acceptable license application would
have put DOE in a better position to submit the application within the time
frames set out in the law, and to respond to questions and challenges that may
emanate from the statutory review process subsequent to the president's
recommendation.
DOE is unlikely to achieve its goal of opening a
repository at Yucca Mountain by 2010. On the basis of DOE's managing
contractor's September 2001 reassessment, sufficient time would not be
available for DOE to obtain a license from NRC and construct enough of the
repository to open it in 2010. Another key factor is whether DOE will be able to
obtain the increases in annual funding that would be required to open the
repository by 2010. Because of the uncertainty of meeting the 2010 goal, DOE is
exploring alternative approaches, such as developing surface facilities for
storing waste at the site until sufficient underground disposal facilities can
be constructed. Had DOE elected to defer a site recommendation until it was
closer to having an acceptable license application, it could have ensured that
the site recommendation was based on the approach to developing a repository
that it intends to follow. This would have enabled DOE to develop an estimated
schedule to design and build the preferred approach and to estimate its cost,
including the annual funding requirements, as part of the information on which
to make a site recommendation.
DOE currently does not have a reliable estimate of when,
and at what cost, a license application can be submitted or a repository can be
opened because DOE stopped using its cost and schedule baselines to manage the
site investigation in 1997. DOE needs to reestablish a baseline for the
repository program that accounts for the outstanding technical work needed to
prepare an acceptable license application and the estimated schedule and cost to
achieve this milestone. In conjunction, DOE needs to use the baseline as a tool
for managing the program, in accordance with the department's policies and
procedures for managing major projects. Therefore, our December 2001 report
recommended that the secretary of energy reestablish the baseline through the
submission of a license application and follow the department's management
requirements, including a formal procedure for changing program milestones.
According to DOE, it is currently in the process of establishing a new baseline
for the nuclear waste program.
Recognizing the critical need to address the issue of
nuclear waste disposal, the Congress enacted the Nuclear Waste Policy Act of
1982 to establish a comprehensive policy and program for the safe, permanent
disposal of commercial spent fuel and other highly radioactive wastes in one or
more mined geologic repositories. The act created the Office of Civilian
Radioactive Waste Management within DOE to manage its nuclear waste program.
Amendments to the act in 1987 directed DOE to investigate only the Yucca
Mountain site.
The Nuclear Waste Policy Act also set out important and
complementary roles for other federal agencies:
·
The Environmental Protection Agency (EPA) was required to
establish health and safety standards for the disposal of wastes in
repositories. EPA issued standards for the Yucca Mountain site in June 2001 that
require a high probability of safety for at least 10,000 years.
·
NRC is responsible for licensing and regulating repositories to
ensure their compliance with EPA's standards. One prerequisite to the
secretary's recommendation was obtaining NRC's preliminary comments on the
sufficiency of DOE's site investigation for the purpose of a license
application. NRC provided these comments on November 13, 2001. If the site is
approved, then NRC, upon accepting a license application from DOE, has 3 to 4
years to review the application and decide whether to issue a license to
construct, and then to operate, a repository at the site.
·
The Nuclear Waste Technical Review Board (the board) reviews the
technical and scientific validity of DOE's activities associated with
investigating the site and packaging and transporting wastes. The board must
report its findings and recommendations to the Congress and the secretary of
energy at least twice each year, but DOE is not required to implement these
recommendations.
DOE has designated the nuclear waste program, including
the site investigation, as a "major" program that is subject to senior
management's attention and to its agencywide guidelines for managing such
programs and projects. The guidelines require the development of a cost and
schedule baseline, a system for managing changes to the baseline, and
independent cost and schedule reviews. DOE is using a management contractor to
carry out the work on the program. The contractor develops and maintains the
baseline, but senior DOE managers must approve significant changes to cost or
schedule estimates. In February 2001, DOE hired Bechtel SAIC Company, LLC (Bechtel),
to manage the program and required the contractor to reassess the remaining
technical work and the estimated schedule and cost to complete this work.
DOE
Will Not Be Ready to Submit a License Application within the Statutory
Time Frame
|
DOE is not prepared to submit an acceptable license
application to NRC within the statutory limits that would take effect if the
site is approved. Specifically, DOE has entered into 293 agreements with NRC to
gather and/or analyze additional technical information in preparation for a
license application that NRC would accept. DOE is also continuing to address
technical issues raised by the board. In September 2001, Bechtel concluded,
after reassessing the remaining technical work, that DOE would not be ready to
submit an acceptable license application to NRC until January 2006. DOE did not
accept the 2006 date. Instead, it
directed the contractor to prepare a new plan for submitting a license
application to NRC by December 2004. DOE's
current plan is that, by the end of September 2002, Bechtel will develop, and
DOE will review and approve, a new technical, cost, and schedule baseline for
submitting a license application to NRC in December 2004.
Moreover, while a site recommendation and a license
application are separate processes, DOE will need to use essentially the same
data for both. Also, the act states that
the president's recommendation to the Congress is that he considers the site
qualified for an application to NRC for a license. The president's
recommendation also triggers an express statutory time frame that requires DOE
to submit a license application to NRC within about 5 to 8 months.
DOE
Lacks Information for a License Application
|
The 293 agreements that DOE and NRC have negotiated
address areas of study within the program where NRC's staff has determined
that DOE needs to collect more scientific data and/or improve its technical
assessment of the data. According to NRC, as of March 2002, DOE had satisfactorily completed work on 38 of these
agreements and could resolve another 22 agreements by September 30 of this year.
These 293 agreements generally relate to uncertainties about three aspects of
the long-term performance of the proposed repository: (1) the expected lifetime
of engineered barriers, particularly the waste containers; (2) the physical
properties of the Yucca Mountain site; and (3) the supporting information for
the mathematical models used to evaluate the performance of the planned
repository at the site.
The uncertainties related to engineered barriers revolve
around the longevity of the waste containers that would be used to isolate the
wastes. DOE currently expects that these containers would isolate the wastes
from the environment for more than 10,000 years. Minimizing uncertainties about
the container materials and the predicted performance of the waste containers
over this long time period is especially critical because DOE's estimates of
the repository system's performance depend heavily on the waste containers, in
addition to the natural features of the site, to meet NRC's licensing
regulations and EPA's health and safety standards.
The uncertainties related to the physical characteristics
of the site center on how the combination of heat, water, and chemical processes
caused by the presence of nuclear waste in the repository would affect the flow
of water through the repository.
The NRC staff's concerns about DOE's mathematical
models for assessing the performance of the repository primarily relate to
validating the models; that is, presenting information to provide confidence
that the models are valid for their intended use and verifying the information
used in the models. Performance assessment is an analytical method that relies
on computers to operate mathematical models to assess the performance of the
repository against EPA's health and safety standards, NRC's licensing
regulations, and DOE's guidelines for determining if the Yucca Mountain site
is suitable for a repository. DOE uses the data collected during site
characterization activities to model how a repository's natural and engineered
features would perform at the site.
According to DOE, the additional technical work
surrounding the 293 agreements with NRC's staff is an insignificant addition
to the extensive amount of technical work already completed-including some 600
papers cited in one of its recently published reports and a substantial body of
published analytic literature. DOE does not expect the results of the additional
work to change its current performance assessment of a repository at Yucca
Mountain.
From NRC's perspective, however, the agreements
provided the basis for it to give DOE its preliminary comments on the
sufficiency of DOE's investigation of the Yucca Mountain site for inclusion in
a future license application. In a November 13, 2001, letter to the under
secretary of energy, the Chairman of the NRC commented that
"[a]lthough significant additional work is needed prior to
the submission of a possible license application, we believe that agreements
reached between DOE and NRC staff regarding the collection of additional
information provide the basis for concluding that development of an acceptable
license application is achievable."
The board has also consistently raised issues and
concerns over DOE's understanding of the expected lifetime of the waste
containers, the significance of the uncertainties involved in the modeling of
the scientific data, and the need for an evaluation and comparison of a
repository design having a higher temperature with a design having a lower
temperature. The board continues to reiterate these concerns in its reports. For
example, in its most recent report to the Congress and the secretary of energy,
issued on January 24, 2002, the board concluded that, when DOE's technical and
scientific work is taken as a whole, the technical basis for DOE's repository
performance estimates is "weak to moderate" at this time. The board added
that gaps in data and basic understanding cause important uncertainties in the
concepts and assumptions on which DOE's performance estimates are now based;
providing the board with limited confidence in current performance estimates
generated by DOE performance assessment model.
As recently as May 2001, DOE projected that it could
submit a license application to NRC in 2003. It now appears, however, that DOE
may not complete all of the additional technical work that it has agreed to do
to prepare an acceptable license application until January 2006. In September
2001, Bechtel completed, at DOE's direction, a detailed reassessment in an
effort to reestablish a cost and schedule baseline. Bechtel estimated that DOE
could complete the outstanding technical work agreed to with NRC and submit a
license application in January 2006. This date, according to the contractor, was
due to the cumulative effect of funding reductions in recent years that had
produced a ".growing bow wave of incomplete work that is being pushed into
the future." Moreover, the contractor's report said, the proposed schedule
did not include any cost and schedule contingencies. The contractor's estimate
was based on guidance from DOE that, in part, directed the contractor to assume
annual funding for the nuclear waste program of $410 million in fiscal year
2002, $455 million in fiscal year 2003, and $465 million in fiscal year 2004 and
thereafter. DOE did not accept this
estimate because, according to program officials, the estimate would extend the
date for submitting a license application too far into the future. Instead, DOE
accepted only the fiscal year 2002 portion of Bechtel's detailed work plan and
directed the contractor to prepare a new plan for submitting a license
application to NRC by December 2004.
Essentially
the Same Information Is Needed for a Site Recommendation and a License
Application
|
Under the Nuclear Waste Policy Act, DOE's site
characterization activities are to provide information necessary to evaluate the
Yucca Mountain site's suitability for submitting a license application to NRC
for placing a repository at the site. In implementing the act, DOE's
guidelines provide that the site will be suitable as a waste repository if the
site is likely to meet the radiation protection standards that NRC would use to
reach a licensing decision on the proposed repository. Thus, as stated in the
preamble (introduction) to DOE's guidelines, DOE expects to use essentially
the same data for the site recommendation and the license application.
In addition, the act specifies that, having received a
site recommendation from the secretary, the president shall submit a
recommendation of the site to the Congress if the president considers the site
qualified for a license application. Under the process laid out in the Nuclear
Waste Policy Act, once the secretary makes a site recommendation, there is no
time limit under which the president must act on the secretary's
recommendation. However, when the president recommended, on February 15, that
the Congress approve the site, specific statutory time frames were triggered for
the next steps in the process. Figure 1 shows the approximate statutory time
needed between a site recommendation and submission of a license application and
the additional time needed for DOE to meet the conditions for an acceptable
license application. The figure assumes that the Congress overrides the
state's disapproval of April 8, 2002. As
shown in the figure, Nevada had 60 days-until April 16-to disapprove the
site. The Congress now has
90 days (of continuous session) from that date in which to enact
legislation overriding the state's disapproval. If the Congress overrides the
state's disapproval and the site designation takes effect, the next step is
for the secretary to submit a license application to NRC within 90 days after
the site designation is effective. In total, these statutory time frames provide
about 150 to 240 days, or about 5 to 8 months, from the time the president makes
a recommendation to DOE's submittal of a license application. On the basis of
Bechtel's September 2001 program reassessment, however, DOE would not be ready
to submit a license application to NRC until January 2006.
Figure 1: Comparison of Statutory Site
Approval Process with DOE's Projected Schedule

aNinety calendar days of continuous
session of the Congress.
DOE states that it may be able to open a repository at
Yucca Mountain in 2010. The department has based this expectation on submitting
an acceptable license application to NRC in 2003, receiving NRC's
authorization to construct a repository in 2006, and constructing essential
surface and underground facilities by 2010. However, Bechtel, in its September
2001 proposal for reestablishing technical, schedule, and cost baselines for the
program, concluded that January 2006 is a more realistic date for submitting a
license application. Because of uncertainty over when DOE may be able to open
the repository, the department is exploring alternatives that might still permit
it to begin accepting commercial spent fuel in 2010.
Extension
of License Application Date Will Likely Postpone 2010 Repository Goal
|
An extension of the license application date to 2006
would almost certainly preclude DOE from achieving its long-standing goal of
opening a repository in 2010. According to DOE's May 2001 report on the
program's estimated cost, after submitting a license application in 2003, DOE
estimates that it could receive an authorization to construct the repository in
2006 and complete the construction of enough surface and underground facilities
to open the repository in 2010, or 7 years after submitting the license
application. This 7-year estimate from submittal of the license application to
the initial construction and operation of the repository assumes that NRC would
grant an authorization to construct the facility in 3 years, followed by 4 years
of construction. Assuming these same estimates of time, submitting a license
application in January 2006 would extend the opening date for the repository
until about 2013.
Furthermore, opening the repository in 2013 may be
questionable for several reasons. First, a repository at Yucca Mountain would be
a first-of-a-kind facility, meaning that any schedule projections may be
optimistic. DOE has deferred its original target date for opening a repository
from 1998 to 2003 to 2010. Second, although the Nuclear Waste Policy Act states
that NRC has 3 years to decide on a construction license, a fourth year may be
added if NRC certifies that it is necessary. Third, the 4-year construction time
period that DOE's current schedule allows may be too short. For example, a
contractor hired by DOE to independently review the estimated costs and schedule
for the nuclear waste program reported that the 4-year construction period was
too optimistic and recommended that the construction phase be extended by a
year-and-a-half.
Bechtel anticipates a 5-year period of construction between the receipt of a
construction authorization from NRC and the opening of the repository. A 4-year
licensing period followed by 5 years of initial construction could extend the
repository opening until about 2015.
Finally, these simple projections do not account for any
other factors that could adversely affect this 7- to 9-year schedule for
licensing, constructing, and opening the repository. Annual appropriations for
the program in recent years have been less than $400 million. In contrast,
according to DOE, it needs between $750 million and $1.5 billion in annual
appropriations during most of the 7- to 9-year licensing and construction period
in order to open the repository on that schedule. In its August 2001 report on
alternative means for financing and managing the program, DOE stated that unless
the program's funding is increased, the budget might become the "determining
factor" whether DOE will be able to accept wastes in 2010.
In part, DOE's desire to meet the 2010 goal is linked
to the court decisions that DOE-under the Nuclear Waste Policy Act and as
implemented by DOE's contracts with owners of commercial spent fuel-is
obligated to begin accepting spent fuel from contract holders not later than
January 31, 1998, or be held liable for damages. Courts are currently assessing
the amount of damages that DOE must pay to holders of spent fuel disposal
contracts. Estimates of potential damages for the estimated 12-year delay from
1998 to 2010 range widely from the department's estimate of about
$2 billion to $3 billion to the nuclear industry's estimate of at least
50 billion. The damage estimates are based, in part, on the expectation that DOE
would begin accepting spent fuel from contract holders in 2010. The actual
damages could be higher or lower, depending on when DOE begins accepting spent
fuel.
DOE
Is Reviewing Alternative Ways to Accept Wastes in 2010
|
Because of the uncertainty of achieving the 2010 goal for
opening the Yucca Mountain repository, DOE is examining alternative approaches
that would permit it to meet the goal. For example, in a May 2001 report, DOE
examined approaches that might permit it to begin accepting wastes at the
repository site in 2010 while spreading out the construction of repository
facilities over a longer time period. The report recommended storing wastes on
the surface until the capacity to move wastes into the repository has been
increased. Relatively modest-sized initial surface facilities to handle wastes
could be expanded later to handle larger volumes of waste. Such an approach,
according to the report, would permit partial construction and limited waste
emplacement in the repository, at lower than earlier estimated annual costs, in
advance of the more costly construction of the facility as originally planned.
Also, by implementing a modular approach, DOE would be capable of accepting
wastes at the repository earlier than if it constructed the repository described
in the documents that the secretary used to support a site recommendation.
DOE has also contracted with the National Research
Council to provide recommendations on design and operating strategies for
developing a geologic repository in stages, which is to include reviewing
DOE's modular approach. The council is addressing such issues as the (1)
technical, policy, and societal objectives and risks for developing a staged
repository; (2) effects of developing a staged repository on the safety and
security of the facility and the effects on the cost and public acceptance of
such a facility; and (3) strategies for developing a staged system, including
the design, construction, operation, and closing of such a facility.
In March 2002, the council published an interim report on the study in
which it address a conceptual framework for a generic repository program.
The Council plans to issue a final report this fall, in which it intends
to provide specific suggestions for incorporating additional elements of staged
repository development into DOE's repository program.
DOE's
Current License Application Milestone Date Is Not Supported by the
Program's Baseline
|
As of December 2001, DOE expected to submit the
application to NRC in 2003.
This date reflects a delay in the license application milestone date last
approved by DOE in March 1997 that targeted March 2002 for submitting a license
application. The 2003 date was not formally approved by DOE's senior managers
or incorporated into the program's cost and schedule baseline, as required by
the management procedures that were in effect for the program. At least three
extensions for the license application date have been proposed and used by DOE
in program documents, but none of these proposals have been approved as
required. As a result, DOE does not have a baseline estimate of the program's
schedule and cost-including the late 2004 date in its fiscal year 2003 budget
request-that is based on all the work that it expects to complete through the
submission of a license application.
DOE's guidance for managing major programs and projects
requires, among other things, that senior managers establish a baseline for
managing the program or project. The baseline describes the program's
mission-in this case, the safe disposal of highly radioactive waste in a
geologic repository-and the expected technical requirements, schedule, and
cost to complete the program. Procedures for controlling changes to an approved
baseline are designed to ensure that program managers consider the expected
effects of adding, deleting, or modifying technical work, as well as the effects
of unanticipated events, such as funding shortfalls, on the project's mission
and baseline. In this way, alternative courses of action can be assessed on the
basis of each action's potential effect on the baseline. DOE's procedures
for managing the nuclear waste program require that program managers revise the
baseline, as appropriate, to reflect any significant changes to the program.
After March 1997, according to DOE officials, they did
not always follow these control procedures to account for proposed changes to
the program's baseline, including the changes proposed to extend the date for
license application. According to these same officials, they stopped following
the control procedures because the secretary of energy did not approve proposed
extensions to the license application milestone. As a result, the official
baseline did not accurately reflect the program's cost and schedule to
complete the remaining work necessary to submit a license application.
In November 1999, the Yucca Mountain site investigation
office proposed extending the license application milestone date by 10 months,
from March to December 2002, to compensate for a $57.8 million drop in funding
for fiscal year 2000. A proposed extension in the license application milestone
required the approval of both the director of the nuclear waste program and the
secretary of energy. Neither of these officials approved this proposed change
nor was the baseline revised to reflect this change even though the director
subsequently began reporting the December 2002 date in quarterly performance
reports to the deputy secretary of energy. The site investigation office
subsequently proposed two other extensions of the license application milestone,
neither of which was approved by the program's director or the secretary of
energy or incorporated into the baseline for the program. Nevertheless, DOE
began to use the proposed, but unapproved, milestone dates in both internal and
external reports and communications, such as in congressional testimony
delivered in May 2001.
Because senior managers did not approve these proposed
changes for incorporation into the baseline for the program, program managers
did not adjust the program's cost and schedule baseline. By not accounting for
these and other changes to the program's technical work, milestone dates, and
estimated costs in the program's baseline since March 1997, DOE has not had
baseline estimates of all of the technical work that it expected to complete
through submission of a license application and the estimated schedule and cost
to complete this work. This condition includes the cost and schedule information
contained in DOE's budget request for fiscal year 2003.
When DOE hired Bechtel to manage the nuclear waste
program, one of the contractor's first assignments was to document the
remaining technical work that had to be completed to support the submission of a
license application to NRC and to estimate the time and cost to complete this
work. The contractor's revised, unofficial baseline for the program shows that
it will take until January 2006 to complete essential technical work and submit
an acceptable license application. Also, DOE had estimated that completing the
remaining technical work would add about $1.4 billion to the cumulative cost of
the program, bringing the total cost of the Yucca Mountain project's portion
of the nuclear waste program to $5.5 billion.
As noted earlier, DOE accepted only the fiscal year 2002 portion of the proposed
baseline and then directed the contractor to prepare a plan for submitting a
license application to NRC by December 2004.
Because of these management weaknesses, we recommended in
our December 2001 report that the secretary of energy reestablish the baseline
through the submission of a license application and follow the department's
management requirements, including a formal procedure for changing program
milestones. According to DOE, it is currently in the process of establishing a
new baseline for the nuclear waste program.
Mr. Chairman, this concludes our prepared statement. We
would be happy to respond to any questions that you or members of the
subcommittee may have.
Contacts and Acknowledgments
For further information about this testimony, please contact me at
(202) 512-3841. Dwayne Weigel, Daniel Feehan, Doreen Feldman, Susan Irwin, and
Robert Sanchez also made key contributions to this statement.
Printer
Friendly
Comment
On This Page
Related
Documents
|