|
Subcommittee on Energy and Air Quality
March 27, 2001
1:00 PM
2123 Rayburn House Office Building
Summary
Nuclear power is the second largest supplier of U.S. electricity
generation, accounting for 20 percent of all generation by electricity producers
and cogenerators in 2000. No new nuclear capacity has been completed in the
United States since 1996. However, generation has continued to grow since that
time due to improved performance at existing plants. The average time required
for refueling and regular maintenance has dropped considerably, and unplanned
outages have been reduced. Existing plants are also making technical
improvements that can increase their maximum capacity by up to 15 percent, and
therefore provide more electricity.
The contribution of nuclear power to the U.S. electricity supply
is expected to decline over the next 20 years, as some existing nuclear units
begin to retire. Nuclear power is projected to provide 11 percent of the nation's
electricity generation in 2020, less than coal and natural gas. No new nuclear
construction is projected to come on line by 2020 due to the higher cost of new
nuclear construction relative to coal- and gas-fired technologies. Twenty seven
units of existing capacity are projected to operate beyond the initial 40 year
license period. Currently 5 nuclear units have received approval by the Nuclear
Regulatory Commission to extend their licenses for an additional 20 years.
Another five units have submitted applications for license renewal, and 28 units
have scheduled future submittals with the NRC through 2004.
The nuclear power industry and the Department of Energy face
challenges in the area of disposing of the high-level nuclear waste. The
Department of Energy is tasked with siting a final repository for the spent fuel
generated by nuclear power, and to take title to the existing waste beginning in
1998. However, the final site has not yet been approved, and an amendment to the
Nuclear Waste Policy Act prohibits the Department from creating an intermediate
storage site prior to siting the final repository. Therefore, there is no
central temporary storage site available, and nuclear generators must continue
storing spent fuel at the reactor site. A number of utilities have filed suit
against the Department due to its delay in beginning to accept spent fuel. The
Department has entered into a settlement with one utility to compensate it for
costs the utility incurred related to the Department's delay. Another
potential regulatory issue for nuclear power is the expiration of the
Price-Anderson Act in 2002, which will revisit the issue of liability in the
event of a nuclear accident, as well as the amount of coverage required for each
nuclear power plant.
STATEMENT
I appreciate the opportunity to appear before you today to
discuss current and future prospects for nuclear power in the United States.
The Energy Information Administration (EIA) is an autonomous
statistical and analytical agency within the Department of Energy. We are
charged with providing objective, timely, and relevant data, analysis, and
projections for the use of the Department of Energy, other Government agencies,
the U.S. Congress, and the public. We do not take positions on policy issues,
but we do produce data and analysis reports that are meant to help policy makers
determine energy policy. Because we have an element of statutory independence
with respect to the analyses that we publish, our views are strictly those of
EIA. We do not speak for the Department, nor for any particular point of view
with respect to energy policy, and our views should not be construed as
representing those of the Department or the Administration. However, EIA's
baseline projections on energy trends are widely used by Government agencies,
the private sector, and academia for their own energy analyses.
The Committee has requested information about current and future
utilization of nuclear power for electricity generation, statutory and
regulatory provisions that impact the use of nuclear power, the prospects for
using nuclear power to meet future generation needs, and the role of nuclear
power in a comprehensive national energy policy. EIA collects and interprets
data on the current energy situation, and produces both short-term and long-term
energy projections. The projections in this testimony are from our Annual
Energy Outlook 2001, released late last year. The Annual Energy Outlook
provides projections and analysis of domestic energy consumption, supply, and
prices through 2020. These projections are not meant to be exact predictions of
the future, but represent a likely energy future, given technological and
demographic trends, current laws and regulations, and consumer behavior as
derived from known data. EIA recognizes that projections of energy markets are
highly uncertain and subject to many random events that cannot be foreseen, such
as weather, political disruptions, strikes, and technological breakthroughs. In
addition, long-term trends in technology development, demographics, economic
growth, and energy resources may evolve along a different path than assumed in
the Annual Energy Outlook. Many of these uncertainties are explored
through alternative cases.
The Current Situation
Supply, Demand and Prices
The United States currently has 104 operable nuclear units,
totaling 97.5 gigawatts of capacity. Electricity generation from nuclear power
increased in 2000 to 754 billion kilowatthours, and the average capacity factor
for U.S. nuclear power plants in 2000 was the highest in history at 89% (Figure
1). Through 1990, the average annual capacity factor was less than 70%.
Increased performance has been achieved through improved operations resulting in
shorter and fewer outages. During 1999, the average time required to refuel a
nuclear reactor was 42 days, and nearly all nuclear plants operate for 18 months
between refuelings. During the 1970's and 80's the average refueling cycle was
more typically 12 months, resulting in more frequent outages. The industry's
median unplanned capacity loss factor was just two percent in 1999.
In 1999, the production costs (expenditures for fuel and
operations and maintenance) at nuclear power plants averaged 1.9 cents per
kilowatthour (kwh), roughly the same as the operating costs of coal-fired power
plants, and about two-thirds the operating costs of oil and natural gas-fired
steam plants.
Fuel costs are a small part of the operating costs of a nuclear
power plant. In 1999, U.S. utilities purchased a total of 47.9 million pounds of
U3 O8e (equivalent) at an average price of $11.63 per pound U3O8e. Foreign
sources supplied 76 percent of the deliveries, mainly from Canada, Australia and
Russia. Nuclear operators tend to purchase uranium on long-term contracts and
the prices are not particularly volatile. Utilities loaded fuel assemblies
containing 58.8 million pounds U3O8e into reactors during 1999, and had
inventories of 58.2 million pounds at year-end. U.S. suppliers had 68.8 million
tons of uranium inventories at year-end 1999. EIA estimates of U.S. uranium
reserves total 1,182 million pounds, although the estimated costs of mining and
milling the uranium are higher than current market prices. During 1999, a total
of 4.5 million pounds U3O8e of uranium were produced by mining, and there were
nine commercially operating uranium mines in the United States. Once the uranium
is purchased, it must then be enriched (increasing the concentration of the
fissionable isotope) before it can be used as nuclear fuel. U.S. facilities
provided 46 percent of U.S. utilities enrichment services in 1999, and foreign
enrichment plants the remaining 54 percent. Enrichment services are also
primarily obtained through long-term service contracts.
Legislative and Regulatory Challenges
The Nuclear Regulatory Commission (NRC) oversees the licensing
and operation of nuclear power plants. The typical operating license for a
nuclear plant was issued for 40 years. With the first wave of current plants
brought online in the 1970s, many of these units could be facing retirement in
the near future. However, the NRC has provided a process for nuclear plant
owners to apply for renewal of their operating licenses, adding another 20 years
to the licensed lifetime. In March of 2000, Baltimore Gas and Electric's two
Calvert Cliffs units were the first nuclear reactors to receive license renewal,
extending their license expiration dates to 2034 and 2036, respectively. Also in
2000, three units at Oconee received license renewal approval, and five other
units have applications submitted. Future submittals have been scheduled for
roughly 40 percent of current plants through 2004. The NRC has created a
streamlined process to review applications, and the total time from application
submitted to approval has been just under two years. The cost to the owner of
pursuing a license renewal has been estimated at between $10 million and $20
million per reactor, and requires detailed descriptions of expected aging
effects and how they will be addressed to maintain safe operation. The renewal
approval does not require the company to undertake potential capital
expenditures to keep the plant running the additional time, which could be
substantially more than the cost of obtaining the license. So the eventual
retirement date of any plant will likely be based on the economics of its
operation rather than the actual date on the license. To date, the longest a
commercial nuclear plant in the United States has operated is 33 years.
Nuclear waste disposal is a challenge that is faced primarily
when the plant is shut down and waiting to be decommissioned. Low level waste (LLW)
disposal is the responsibility of the states where the waste is generated.
Interstate compacts have been created to jointly develop sites for disposal;
however, no new sites have been opened even though the Low Level Radioactive
Waste Policy Act stated that disposal facilities could refuse to accept waste
from outside their compacts beginning in 1992. Currently, only three low-level
waste sites exist: one in Hanford, Washington, which only accepts waste from
states in the Northwest Compact in which it resides, and the neighboring Rocky
Mountain Compact; one in Clive, Utah, which is only licensed to accept the
lowest level - Class A - waste, and one in South Carolina, which is still
accepting all classes of LLW from all states except North Carolina. States that
do not have access to disposal facilities are likely to require the waste
generators to store their waste on-site until new disposal sites are available.
South Carolina has recently joined a compact with Connecticut and New Jersey,
and has enacted a state law to phase out acceptance of non-compact waste by
2008. The site in Utah, operated by Envirocare, has applied for a license to
accept the higher classes of waste, and has no plans to limit acceptance of the
waste. Low-level waste disposal issues are important because they affect the
cost and timing of decommissioning nuclear power plants.
The Department of Energy is working on siting a repository for
spent nuclear fuel and high-level waste. The proposed waste site at Yucca
Mountain, NV is still undergoing site characterization, to determine if the site
is suitable and should be recommended for development. The soonest this proposed
facility could begin accepting the waste is 2010. The initial storage of the
spent fuel assemblies, once removed from a reactor, is in steel lined pools at
the reactor site. However, these are quickly being filled to capacity at most
reactors. For temporary storage, dry cask containers have been developed and
licensed by the NRC to store the used fuel assemblies. Some of these storage
containers should be suitable for transporting the waste once the final
repository is sited. The lack of a final repository is not likely to force any
operating nuclear reactors to shut down early, but will require the owners to
purchase, and receive approval to install, the temporary storage containers
on-site.
Finally, the Price-Anderson Act expires in 2002 and could create
barriers to new construction if it is not extended in its current form. The
Price-Anderson Act was enacted into law in 1957, as part of the Atomic Energy
Act, to meet two objectives: to remove any deterrents to private sector
participation in nuclear energy due to the threat of large liability claims in
the event of a catastrophic nuclear accident, and to ensure that adequate funds
are available to the public if such an accident were to occur. The Act limits
liability to third parties in the event of a nuclear accident to $9.43 billion.
It also provides for a series of retroactive assessments paid by all nuclear
utilities if the total liability exceeds the amount of primary coverage. If the
Act is not extended, coverage for existing units would continue as provided by
the Act, but any new nuclear units would not be covered. The Price-Anderson Act
has been extended three times since 1957, and current legislation has been
proposed in the Senate that includes the extension of the Act through 2012.
The Outlook
The Annual Energy Outlook 2001 (AEO2001) reference case projects
U.S. energy supply, demand and prices through 2020. It assumes a continuation of
current laws and regulations, and provides alternative scenarios to deal with
uncertainty in the assumptions. It is expected that recent trends in improved
performance will be maintained, resulting in average capacity factors for
operating plants of 90 percent by the last years of the forecast. The long-term
projection, however, is for a decline in total generation from nuclear power as
some existing nuclear reactors are retired and replaced by other, mainly
gas-fired, generating units (Figure 2).
Electricity demand is projected to grow at an annual average
rate of 1.8 percent between now and 2020. To meet this demand, and to replace
retirements of older generating units, EIA projects 413 gigawatts of new
generating capacity will be needed (including cogeneration capacity). Of this
new capacity, 92 percent is projected to be combined-cycle or combustion turbine
technology fueled by natural gas. About five percent of the new capacity is
expected to be coal-fired, and the remaining three percent renewable
technologies. The projected operating cost of a new nuclear reactor (including
capital recovery) is about 6 cents per kilowatthour, higher than that for coal
or combined-cycle capacity which are roughly 4 cents per kilowatthour (Figure
3). Gas-fired units are favored particularly in restructured electricity markets
due to their lower capital costs, higher efficiencies, shorter construction
times, and better load following characteristics.
Within the EIA forecast, nuclear units are forecast to retire
when their operation is no longer economic relative to replacement capacity. The
forecast incorporates future aging-related costs that could be incurred as
plants consider operating beyond 40 years. In the reference case, nuclear plants
are assumed to incur additional capital costs of $14 per kilowatt (kw) per year
after 40 years, and increase to $25/kw per year after 50 years. These costs are
reduced significantly for individual units if they have already incurred major
capital investments related to plant upgrades. The aging related costs are
similar in magnitude to annual capital additions assumed for existing fossil
plants ($4-5/kw for gas plants, $10/kw for oil/gas steam units and $16/kw for
coal plants, on average). In the reference case, 27 percent of current capacity
is forecast to retire by 2020, mainly after 2010. Of this retiring capacity, one
nuclear plant is projected to retire before the end of its 40 year life, 30
units are forecast to retire at the end of their current license expiration and
2 units are projected to retire ten years after their current license expiration
(implying a license renewal was received). Another 25 units have original
licenses that expire by 2020, but are forecast to receive license renewal and
extend their operation beyond 2020.
Because the U.S. nuclear industry has no experience operating
reactors beyond 40 years (the oldest operating reactor today is just over 30
years old), future operating costs and capital investments required are unknown.
Due to the uncertainties surrounding future aging-related costs, several cases
were developed to further analyze the effects on electricity supply due to
differing assumptions regarding the costs of future operation (Figure 4). These
results provide a range of possible futures for existing nuclear power. In the
low nuclear case it was assumed that aging related costs would begin earlier,
with capital additions of $5/kw per year starting at age 30. A total of 18
additional units were projected to be retired through 2020 relative to the
reference case. Additional fossil-fired capacity was projected to be built to
replace the retiring nuclear capacity, and the carbon emissions from electric
generators increased by two percent (16 million metric tons carbon equivalent)
above the reference case in 2020. In the high nuclear case, aging related costs
were assumed to be lower by 25 percent, resulting in more plants projected to
operate beyond their initial license life. In the high nuclear case only 11
units were projected to retire through 2020 ( 9 percent of current capacity).
About 14 gigawatts of fossil-fired capacity (roughly 47 units at 300 megawatts
each) would no longer be required, relative to the reference case, and carbon
emissions from electric generators would be reduced by two percent (16 million
metric tons carbon equivalent) by 2020.
There are additional uncertainties affecting other generating
industries that could change the competitiveness of nuclear power. Current
natural gas prices are much higher than normal in response to low levels of gas
storage, unusually cold weather and supply issues. The AEO2001 forecasts that
this situation will reverse over the next few years, as increased drilling and
production occurs, and that gas prices will return to more typical levels by
2004. Therefore, forecasts of the cost of new gas-fired capacity later in the
forecast are based on gas prices below the current levels. More existing nuclear
power plants would be economic if current gas prices remained throughout the
forecast period, resulting in fewer retirements. However, it is expected that
this tight supply situation for natural gas will dissipate before 2010, when the
retirement decisions for nuclear units start being made.
The electric generation sector may also face restrictions on the
emissions of various pollutants in the future. Since the AEO2001 forecast
incorporates current laws and regulations, it requires the electric sector to
meet sulfur dioxide and nitrogen oxide restrictions as specified in the Clean
Air Act. The summer season cap on nitrogen oxide (for 22 states) will be imposed
in 2004 by the Environmental Protection Agency (EPA). Because these reductions
are being met by existing fossil plants by adding the necessary control
equipment, their operation and costs are not greatly affected. If additional
emissions were targeted in the future for reduction, such as carbon dioxide, a
large number of coal plants would be retired and replaced mainly by gas-fired
technology, leading to higher natural gas prices. This situation would provide
an economic incentive to continue operating more of the existing nuclear power
plants.
For example, the EIA recently performed an analysis of
strategies for reducing multiple emissions at power plants, at the request of
then-Representative David M. McIntosh, Chairman of the Subcommittee on National
Economic Growth, Natural Resources, and Regulatory Affairs of the House
Government Reform Committee. In this report, EIA was asked to provide an
analysis of proposals to reduce sulfur dioxide (SO2) and nitrogen oxide (NOx) by
75 percent from 1997 levels, and carbon dioxide (CO2) to either 1990 levels or 7
percent below 1990 levels, similar to the general requirements of the Kyoto
protocol, but restricted to emissions by electric generators. In order to comply
with the CO2 cap, the industry was projected to dramatically shift away from
coal to natural gas, and to a lesser extent, renewables. This analysis also
showed fewer nuclear retirements (9 percent of current capacity) by 2020, as the
higher natural gas prices (as much as 63 percent higher than the reference case
in 2010) and CO2 allowance prices made it economical to continue operating more
of the existing capacity. This scenario assumed the AEO2001 reference case
aging-related costs for nuclear plants, however, the nuclear capacity forecast
was similar to the high nuclear case due to the emissions targets and higher
natural gas prices. At the request of the Subcommittee, this analysis assumed
that no new nuclear power plants would be built throughout the forecast period.
Projections of the cost of building new nuclear capacity is
difficult, due to the length of time since a new unit has been ordered in the
United States, and the lack of experience in building new designs. The AEO2001
reference case bases the cost of a new nuclear unit on the advanced passive
reactor design (AP600), which has been approved by the NRC as part of its
standardized design certification. This design has evolved from the current
operating designs, but also includes passive safety features and is based on a
smaller size (600 megawatts). The initial overnight capital cost (in 1999
dollars) of the AP600 is assumed to be $1730 per kilowatt, compared to $1020 to
$1220/kw for a coal-fired unit and $420 to $530/kw for a gas-fired combined
cycle unit. Contingency factors are applied to the costs of all new capacity,
and are made up of two components - a project contingency factor, which is
applied throughout the forecast to account for delays during construction due to
unforseen problems such as weather or labor issues, and a technological optimism
factor, which is only applied to the first four units built of a new design to
account for the tendency to underestimate costs for new technologies. Capital
costs decline over time as new capacity is built and experience is gained.
However, because the initial cost for the advanced nuclear technology is much
higher than other available technologies, it is not economic to build nuclear
units in the reference case.
The Department of Energy's Office of Nuclear Energy has
developed long-term cost goals for these evolutionary designs that are lower
than current estimates. An alternative nuclear cost case was developed assuming
the cost of the new nuclear technology was $1500/kw initially, falling to $1200/kw
by 2015, with a ten percent project contingency factor applied to these costs.
In addition, cases were considered assuming both 3 and 4 year construction
times. In these cases the nuclear
technology was closer to being competitive with coal and gas-fired capacity
(Figure 5); one new unit was projected to be built in the last years of the
forecast under the assumption of a 3 year lead time. (Nuclear units were not
economic under a four year lead time assumption.)
Worldwide, work has been developing on a more revolutionary new
commercial nuclear power technology, known as the pebble bed modular reactor.
South Africa's state-owned utility has been working on the technology since
1993, but it has recently gained the interest of foreign energy policymakers as
well as potential investors. One U.S. based company, PECO Energy, has joined
with British Nuclear Fuels Corporation in making financial commitments to the
venture. PECO's parent company, Exelon Corporation, has begun discussions with
the NRC about building PBMRs in the United States. The economics are expected to
improve for this technology because of the plant's small, modular design (110
megawatts each). The design incorporates passive safety features and would have
higher thermal efficiency than existing nuclear plants, requiring less fuel and
producing less waste. The estimates of construction costs ($1000/kw) would be
very competitive with new coal-fired technologies available in the United
States, if they could be attained. The construction costs would still be almost
double that of a new gas combined-cycle unit ($530/kw). Ultimately, this design
is still untested, and its future will be determined in large part by the
success or failure of the South African demonstration project, scheduled for
completion in 2005.
Conclusion
While nuclear power today provides roughly one-fifth of the
nation's electricity generation, that share is expected to drop over the next
two decades as some existing units are retired and replaced by other generating
technologies. Coal will remain a large supplier of electricity, and natural gas
is expected to greatly increase its proportion of electricity generation. While
operating performance at individual nuclear units is expected to remain high,
total output from nuclear plants is expected to decline by about twenty percent
between now and 2020, as units are removed from service.
The ability to relicense existing nuclear plants for an
additional twenty years of operation could extend the operating lives of current
reactors, and delay retirements. However, achieving new orders for nuclear
plants based solely on economics is unlikely at this time due to the high
construction costs of the technology, as well as uncertainties related to costs,
safety and waste. The challenge of waste disposal is faced by existing nuclear
power plants as they continue to store high level waste on-site, waiting for
site approval and construction of the permanent waste repository required by the
Nuclear Waste Policy Act.
Thank you, Mr. Chairman and members of the Subcommittee. I will
be happy to answer any questions you may have.
Printer
Friendly
Comment
On This Page
Related
Documents
|