Source:
GAO's analysis of OPS data.
|
Traditionally,
OPS carried out its oversight responsibility by requiring all pipeline
operators to comply with uniform, minimum standards.
Recognizing that pipeline operators face different risks depending on
such factors as location and the product they carry, OPS began exploring the
concept of a risk-based approach to pipeline safety in the mid-1990s.
In 1996, the Accountable Pipeline Safety and Partnership Act directed
OPS to establish a demonstration program to test a risk-based approach.
The Risk Management Demonstration Program went beyond OPS'
traditional regulatory approach by allowing individual companies to identify
and focus on risks to their pipelines. Since
the program's initiation in 1997, OPS has approved six demonstration
projects.
OPS
Has Made Progress in Implementing Integrity Management Programs and Other
Initiatives
Partly
on the basis of OPS' experience with the Risk Management Demonstration
Program, the agency has moved forward with a new regulatory approach that
requires pipeline operators to comprehensively identify and address risks to
the segments of their pipelines that are located in "high consequence
areas" where a leak or rupture would have the greatest impact.
This approach requires individual pipeline operators to develop and
follow an integrity management program. Each
program must contain specific elements, including a baseline assessment of all
pipelines that could affect high consequence areas, periodic reassessment of
these pipeline segments, prompt action to address any problems identified in
the assessments, and measures of the program's effectiveness.
Although
OPS has issued final rules requiring integrity management programs for
operators of hazardous liquid pipelines, the agency has not issued a proposed
rule for operators of gas transmission pipelines. In December 2000, OPS issued a final rule for operators of
"large" hazardous liquid pipelines, defined as pipeline systems of at
least 500 miles. Under this rule,
individual operators were required by December 31, 2001 to identify pipeline
segments that can affect high consequence areas, and then develop a framework
for their integrity management program and a plan for conducting baseline
assessments by March 31, 2002. OPS
issued a similar rule for operators of "small" hazardous liquid pipelines
that are less than 500 miles long on January 16, 2002, with later deadlines. For natural gas transmission pipelines, OPS anticipates
issuing a final rule in fall 2002.
OPS
plans to review and monitor operators' programs for compliance with the
integrity management requirements, but will not formally approve operator
programs. OPS is currently in the
first of a four-phase plan for reviewing and monitoring integrity management
programs for operators of large hazardous liquid pipelines. In
phase 1-scheduled to be completed by the end of April 2002-OPS is
reviewing operators' identification of pipeline segments that impact high
consequence areas. During phase
2-from July 2002 to July 2004-OPS will inspect the more fully developed
framework and assessment plans. After July 2004, OPS plans to monitor operators'
implementation of their individual programs through periodic inspections in
phase 3, and review and respond to notifications from operators of changes in
their programs in phase 4.
OPS
is hiring and training additional inspectors to review and monitor
operators' programs. OPS had 56 inspectors in fiscal year 2001 and plans to hire
an additional 30 inspectors-a 54-percent increase-by the end of fiscal
year 2003. OPS plans to augment
its inspection force with contractor and state support as it develops the
necessary expertise to review and monitor operators' programs.
OPS has also developed a list of training courses that will be required
for federal and state inspectors, and it is currently scheduling this
training. OPS officials
anticipate that it will take about 2 years to provide this training to all
federal and state inspectors.
In
addition to the integrity management programs, OPS is making progress on other
initiatives for improving data, involving states, and increasing the use of
fines. These initiatives are intended to improve pipeline safety and
the agency's oversight.
OPS
Is Taking Action to Improve Data
DOT's
Inspector General, the National Transportation Safety Board, and others have
reported that OPS' data on pipeline incidents and infrastructure are limited
and sometimes inaccurate. For
example, in the past, OPS' incident report forms have used only five
categories of causes for incidents on natural gas distribution pipelines, four
categories for those on natural gas transmission pipelines, and seven
categories for those on hazardous liquid pipelines.
As a result, about one-fourth of all pipeline incidents were attributed
to "other causes," which limited OPS' ability to identify and focus on
the causes of incidents. In
addition, data on the amount of pipeline mileage in various infrastructure
categories (such as age or size) are necessary for a meaningful comparison of
the safety performance of individual pipeline companies.
OPS did not require hazardous liquid pipeline operators to submit this
type of data and did not collect complete data from natural gas pipelines.
Finally, the information on incident reports filed by operators
sometimes changes as the incident investigation proceeds.
OPS did not have a procedure for ensuring that operators submitted
revised reports when needed.
OPS
is taking action to collect data that will allow it to more accurately
determine the causes of incidents, analyze industry trends, and compare the
safety performance of operators. For
example, OPS revised its incident report forms in 2001 for hazardous liquid
and natural gas transmission incidents to include 25 categories of causes and
plans to revise the form for natural gas distribution incidents by the end of
2002. Furthermore, OPS is
assigning an inspector in each region to review incident report forms for
completeness and accuracy, and has instituted new electronic notification
procedures to ensure that operators submit revised incident reports, if
necessary. OPS also plans to
institute annual reports for hazardous liquid pipeline operators, and is in
the process of revising annual report forms for all natural gas pipeline
operators. Finally, OPS is
conducting studies of incident information to improve its understanding of the
causes of incidents. According to
OPS officials, most of these improvements will be implemented for 2002 data.
According
to the Safety Board and industry groups, OPS' initiatives address the
underlying data problems and will enable OPS to better understand the causes
of incidents so the agency can focus its efforts to improve safety.
However, officials from industry groups told us that it will be several
years before OPS has sufficient data to analyze trends in incidents. Officials from the Safety Board also noted that these
initiatives are merely a first step, and they emphasized that OPS should
periodically reassess its forms and procedures and take steps to revise them
as necessary. We are evaluating
OPS' data improvement initiatives as part of our ongoing work.
States
Are Taking a Greater Role in Overseeing Interstate Pipeline Safety Activities
OPS
is allowing more states to help oversee a broader range of interstate pipeline
safety activities. Although OPS relies heavily on state inspectors to oversee
intrastate pipelines, it reduced its reliance on states to inspect interstate
pipelines in the mid-1990s when it moved to a more risk-based, system-wide
approach to inspecting pipelines. At
that time, OPS believed it would be too difficult to coordinate participation
by individual states in the new inspection process. However, in our May 2000 report, we found that allowing
states to participate in interstate pipeline safety inspections could improve
pipeline safety by increasing the frequency and thoroughness of inspections to
detect safety problems. Additionally,
state pipeline safety inspectors are likely to be familiar with pipelines in
their jurisdictions and the potential risks faced by these pipelines.
We recommended that OPS work with state pipeline safety officials to
determine which activities would benefit from state participation and, for
states that are willing to participate, integrate their activities into the
safety program. We also recommended that OPS allow state inspectors to assist
in reviewing the integrity management programs developed by the companies that
operate in their states to help ensure that these companies have identified
and adequately addressed safety risks to their systems.
OPS
responded to our recommendations in 2001 by encouraging more states to oversee
the safety of interstate pipelines in their states.
These states may perform a broad range of oversight activities, such as
inspections of new construction, oversight of rehabilitation projects and
integrity management programs, incident investigation, standard inspections,
and participation in nonregulatory program initiatives.
Other states that want to participate on a smaller scale may apply for
specific, short-term projects, such as inspecting new pipeline construction
projects. As of January 2002, 11
states-up from 8 in 2000-have been approved to participate in all
oversight activities, and an additional 4 states have been approved to
participate on short-term projects.
OPS
Is Increasing its Use of Fines
OPS
is increasing its use of fines for safety violations, thereby reversing a
trend of relying more heavily on less severe corrective actions.
From 1990 to 1998, OPS decreased the proportion of enforcement actions
in which it proposed fines from about 49 percent to about 4 percent.
During this time, the agency increased the proportion of warning
letters and letters of concern from about 33 percent to about 68 percent.
OPS made this change in order to place more emphasis on
"partnering" to improve pipeline safety rather than on punishing
noncompliance. As of May 2000,
OPS could not determine whether this approach was effective in maintaining
compliance with safety regulations. Consequently,
we recommended that DOT determine whether OPS' reduced use of fines had
maintained, improved, or decreased compliance with pipeline safety
regulations.
According
to OPS officials, the agency is not able to determine the impact of its
compliance actions on safety as we recommended because it does not have
sufficient data. Nevertheless, OPS concluded that its decreased reliance on
fines was perceived negatively by the public and Congress, and that the
letters of concern did not allow OPS to adequately address safety concerns.
OPS subsequently changed its enforcement policy to make better use of
its full range of enforcement tools, including increasing the number and
severity of fines. According to
OPS officials, the agency plans to collect data that will allow it to link its
compliance actions with improvements in safety.
We will follow up on OPS' progress in this area during our current
review.
OPS
Has Not Implemented Significant Safety Board Recommendations and Statutory
Requirements
OPS
is taking action on open recommendations from the Safety Board and statutory
requirements, but has still not implemented important recommendations and
requirements. In May 2000, we
reported that OPS historically had the worst response rate-about 69
percent-of any transportation agency to Safety Board recommendations.
These recommendations dealt with a variety of issues that are critical
for pipeline safety, such as requiring operators to periodically inspect
pipelines and install valves to shut down the pipeline in an emergency.
Some of these recommendations were more than a decade old.
OPS has been working to improve its responsiveness over the last
several years by initiating activities in response to the recommendations and
improving communications with the Safety Board.
The Safety Board has been encouraged by OPS' efforts to improve its
responsiveness, particularly in the areas of excavation damage, corrosion
control, and data quality. However,
the Safety Board remains concerned about the amount of time OPS has been
taking to implement recommendations. As
of February 2002, OPS had not implemented 42 recommendations, several of which
date from the late 1980s and deal with issues considered critical to pipeline
safety, such as requiring operators to inspect their pipelines.
OPS
maintains that its progress is better than the Safety Board indicates.
According to OPS officials, the majority of the recommendations deal
with integrity management and excavation damage prevention, which the
agency's ongoing initiatives should fulfill before the end of 2002.
We
also reported in May 2000 that OPS had not implemented 22 out of 49 statutory
requirements that were designed to improve pipeline safety.
Similar to the open Safety Board recommendations, several of these
unfulfilled requirements dated from the late 1980s and early 1990s and were
related to important pipeline safety issues, such as internal inspections and
identification of pipelines in populated or environmentally sensitive areas.
Since May 2000, OPS has been working to complete these requirements.
As of February 2002, 8 of the 22 requirements were closed as a result
of OPS' actions, 9 requirements were still open, and the remaining 5 were
reclassified as "closed" because OPS considered them to be superseded by
amendments or other requirements or because the agency did not believe it was
required to take further action. OPS
plans to fulfill the majority of the open requirements before the end of 2002.
OPS
Faces Major Challenges in Implementing its Initiatives
In
our ongoing work, we are examining several issues that could affect OPS'
ability to implement its integrity management and data improvement initiatives
and, ultimately, fulfill the Safety Board's recommendations and statutory
requirements. These issues
include (1) performance measures for the integrity management approach, (2)
sufficient resources and expertise to oversee operators' integrity
management programs, (3) consistent and effective enforcement of integrity
management program requirements, and (4) requirements for integrity management
programs for operators of gas transmission pipelines.
Performance
measures:
In May 2000, we reported that OPS had not developed programwide
performance measures for the Risk Management Demonstration Program, even
though the act required such measures to demonstrate the safety benefits of
the program. OPS still has not developed such measures.
Despite the lack of quantifiable performance measures for the
demonstration program, OPS moved forward with integrity management programs
and faces the challenge of developing performance measures for this new
approach to regulating pipeline safety. Such measures are essential to determine whether the new
approach is successful and what improvements may be needed. However, OPS does not have a complete and viable database of
information on pipeline incidents and an inventory of pipeline infrastructure
on which to establish certain performance measures.
OPS has taken steps to improve its data, but it may be several years
before the agency can accumulate sufficient data to evaluate trends in the
pipeline industry.
Resources
and expertise: Pipeline
operators are in the best position to develop integrity management programs
that are tailored to their pipelines; however, it is critical for OPS to have
adequate resources and expertise to oversee the programs.
After OPS issues a final rule on integrity management programs for
natural gas transmission pipelines, the agency estimates that there will be
more than 400 hazardous liquid and natural gas pipeline operators with
individual programs in various stages of development.
OPS must ensure that it has a sufficient number of inspectors to
oversee these programs while maintaining its other oversight responsibilities. Moreover, while OPS has resolved to include states in
reviewing and monitoring operators' programs, the agency faces a challenge
to determine how best to leverage federal and state resources and provide
training to state inspectors.
Furthermore,
OPS' integrity management initiative represents a fundamental shift in how
it oversees the pipeline industry. Federal
and state inspectors that are accustomed to using a checklist approach for
inspecting pipelines for compliance with uniform regulations will have to be
trained to evaluate programs that are unique to individual operators.
For example, under the new requirements, operators may use a variety of
inspection techniques to assess the safety of their pipelines.
Inspectors must be familiar with all of these inspection techniques,
know when it is appropriate to use them, and know how to interpret the
results.
Enforcement:
The variability of individual operator programs will make it difficult
for OPS to enforce the requirements of the integrity management program.
OPS' integrity management requirements for hazardous liquid pipelines
allow pipeline operators flexibility to design and implement integrity
management programs based on pipeline-specific conditions and risks.
However, this flexibility will result in unique programs for each
operator and require more judgment on the part of inspectors.
To ensure that the program requirements are consistently and
effectively enforced, OPS is developing a comprehensive set of inspection
protocols that are intended to provide clear criteria to inspector staff for
evaluating the adequacy of operator actions and making enforcement decisions.
As noted previously, OPS believes its staff will need increased
training and expertise to make these types of judgments.
Final
rule for natural gas transmission pipelines:
OPS has issued the final rules requiring integrity management programs
for operators of hazardous liquid pipelines; however, significant differences
between natural gas transmission pipelines and hazardous liquid pipelines
present challenges for OPS in developing a similar rule for operators of
natural gas transmission pipelines. For
example, to facilitate the movement of natural gas under pressure,
transmission pipelines tend to vary more in diameter than hazardous liquid
pipelines. These variations make it more difficult for natural gas
transmission pipelines to accommodate internal inspection devices.
The Interstate Natural Gas Association of America estimates that about
45 percent, or about 145,000 miles, of natural gas transmission pipelines
would require alternative inspection methods because modifying the pipelines
to accommodate internal inspection devices would not be feasible.
OPS plans to identify alternative inspection methods that would be
effective in assessing the integrity of these pipelines.
OPS has 8 months to resolve this issue if it is to meet the goal of
issuing a final rule by the end of 2002.
Observations
We
are encouraged by OPS' recent efforts to improve its oversight of pipeline
safety and believe they are steps in the right direction. However, a number of challenges remain. These challenges include developing performance measures for
the integrity management approach, ensuring sufficient resources and expertise
to oversee operators' integrity management programs, providing consistent
and effective enforcement of integrity management program requirements, and
issuing requirements for integrity management programs for operators of gas
transmission pipelines. It is
imperative for OPS to meet these challenges to ensure the safety of the
nation's pipelines.
-
- - - -
Mr.
Chairman, this concludes my testimony. I
would be pleased to answer any questions you or Members of the Subcommittee
may have.
Contacts
and Acknowledgments
For
information about this testimony, please contact Peter F. Guerrero at (202)
512-4907 or guerrerop@gao.gov.
This statement is available on GAO's home page at http://www.gao.gov.
Individuals making key contributions to this testimony were Helen
Desaulniers, Susan Fleming, Judy Guilliams-Tapia, Michael Horton, Wyatt
Hundrup, and Sara Vermillion.
(545012)